Region: West | Legislative District: 39 | Length: 0.00 mi. | FY 2023 Small City Preservation Program (SCPP) |
Existing Conditions |
TIB Funds | Local Funds | Total Costs | |
---|---|---|---|
Design | 20,000 | 0 | 20,000 |
Right of Way | 0 | 0 | 0 |
Construction | 187,637 | 0 | 187,637 |
Project Totals | $207,637 | $0 | $207,637 |
TIB Participation | Local Match | Minimum Local Match |
---|---|---|
100.0% | 0.0% | 0% |
Work for this segment will include: grind, HMA pavement repair, 2 inch HMA overlay, and other work as necessary for the needed improvements.