City of Bridgeport
FY 2022 Overlay Project
Multiple Locations
TIB Award Amount
$223,667
Region: East   |   Legislative District: 12   |   Length: 0.00 mi. FY 2022 Small City Preservation Program (SCPP)

Existing Conditions

Anticipated Project Costs

  TIB Funds Local Funds Total Costs
Design 25,744 1,356 27,100
Right of Way 0 0 0
Construction 197,923 10,427 208,350
Project Totals $223,667 $11,783 $235,450

Local Match

TIB Participation Local Match Minimum Local Match
95.0% 5.0% 0%

Description of Improvements

Overlay the existing roadway, with subgrade repair (digouts) where necessary. Recent completed work on Foster Avenue between 14th Ave and 17th Ave showed that the roadway lacks a gravel base and the HMA is less than 2 inches thick, so transition planning to connect to side streets would not provide a suitable base for paving. Instead of transition paving, subgrade repair consisting of 6-inches of crushed surfacing top course and 2-inches of HMA will be provided to connect to side streets.