Existing Conditions

Anticipated Project Costs

  TIB Funds Local Funds Total Costs
Design 10,450 550 11,000
Right of Way 0 0 0
Construction 123,006 6,474 129,480
Project Totals $133,456 $7,024 $140,480

Local Match

TIB Participation Local Match Minimum Local Match
95.0% 5.0% 0%

Description of Improvements

This project repairs area of pavement failure and provides a 2-inch overlay of Carbonado-Wilkeson Road between AP Tubbs Road and Town limits