City of Black Diamond
FY 2022 Overlay Project
Multiple Locations
TIB Award Amount
$129,549
Region: Puget Sound   |   Legislative District: 5   |   Length: 0.00 mi. FY 2022 Small City Preservation Program (SCPP)

Existing Conditions

Anticipated Project Costs

  TIB Funds Local Funds Total Costs
Design 3,783 667 4,450
Right of Way 0 0 0
Construction 125,766 22,194 147,960
Project Totals $129,549 $22,861 $152,410

Local Match

TIB Participation Local Match Minimum Local Match
85.0% 15.0% 10%

Description of Improvements

This project repairs areas of pavement failure, provides a 2-inch overlay and upgrades 3 ADA ramps on the following segments: 6th Avenue - Lawson Street to Baker Street Baker Street - 5th Avenue to 6th Avenue Hammond Place - Baker Street to end of road Park Street - 3rd Avenue to 4th Avenue 4th Avenue - Park Street to James Street James Street - 3rd Street to 4th Street