Town of South Cle Elum
FY 2022 Seal Coat Project
Multiple Locations
TIB Award Amount
$27,388
Region: East   |   Legislative District: 13   |   Length: 0.00 mi. FY 2022 Small City Preservation Program (SCPP)

Existing Conditions

Anticipated Project Costs

  TIB Funds Local Funds Total Costs
Design 0 0 0
Right of Way 0 0 0
Construction 27,388 0 27,388
Project Totals $27,388 $0 $27,388

Local Match

TIB Participation Local Match Minimum Local Match
100.0% 0.0% 0%

Description of Improvements

Chip and sweep