Region: West | Legislative District: 19 | Length: 0.00 mi. | FY 2021 Small City Preservation Program (SCPP) |
Existing Conditions |
TIB Funds | Local Funds | Total Costs | |
---|---|---|---|
Design | 0 | 0 | 0 |
Right of Way | 0 | 0 | 0 |
Construction | 125,000 | 15,000 | 140,000 |
Project Totals | $125,000 | $15,000 | $140,000 |
TIB Participation | Local Match | Minimum Local Match |
---|---|---|
89.3% | 10.7% | 5% |
Plane 1" existing asphalt to top of existing concrete road section in this heavily utilized east/west corridor. Prelevel and install 2" HMA overlay. City crew to repair deficient sidewalk and curbs on the south side. Curb height is high on both sides and will allow for 2" overlay. City crews will also replace non-compliant curb ramps and install storm drains at the Chehalis Street intersection before the overlay work commences.