Region: Puget Sound | Legislative District: 5 | Length: 0.00 mi. | FY 2021 Small City Preservation Program (SCPP) |
Existing Conditions |
TIB Funds | Local Funds | Total Costs | |
---|---|---|---|
Design | 2,550 | 450 | 3,000 |
Right of Way | 0 | 0 | 0 |
Construction | 137,551 | 24,274 | 161,825 |
Project Totals | $140,101 | $24,724 | $164,825 |
TIB Participation | Local Match | Minimum Local Match |
---|---|---|
85.0% | 15.0% | 10% |
Grind, 2-inch overlay and pavement repair of the following segments: 232nd Avenue SE - SE 288th St to SE 293rd St SE 312th Street - 224th Avenue SE to End of Road