Town of Friday Harbor
Marguerite Place
Spring St to Park St
TIB Award Amount
$800,000
Region: West   |   Legislative District: 40   |   Length: 0.24 mi. FY 2023 Small City Arterial Program (SCAP)

Existing Conditions

The existing street is showing signs of surface and subgrade failure. There are not any pedestrian facilities and the existing illumination is inadequate. This project connects two arterials in the Town, Spring Street and Guard Street. The Town completed improvements on Marguerite between Park Street and Guard Street in 2020.

Project Funding

  TIB Funds Local Funds Total Costs
Design 91,128 87,177 178,305
Right of Way 10,222 9,778 20,000
Construction 698,650 668,359 1,367,009
Project Totals $800,000 $765,314 $1,565,314

Local Match

TIB Participation Local Match Minimum Local Match
51.1% 48.9% 10%

Description of Improvements

This project will provide an accessible pedestrian connection between residential neighborhoods, daycare, pre-schools, private schools, library, the high school, a church, a baseball park, and professional services. By reconstructing the street and installing sidewalks and illumination the Town will provide a safe and efficient route for motorists and pedestrians.