Town of Friday Harbor
Mullis Street
818 Mullis to Market St
TIB Award Amount
$696,558
Region: West   |   Legislative District: 40   |   Length: 0.15 mi. FY 2021 Small City Arterial Program (SCAP)

Existing Conditions

The existing street is showing signs of failure of both the surface and subgrade through alligator cracking, longitudinal cracks, delamination, and potholes.

Project Funding

  TIB Funds Local Funds Total Costs
Design 83,587 14,751 98,338
Right of Way 0 0 0
Construction 612,971 108,172 721,143
Project Totals $696,558 $122,923 $819,481

Local Match

TIB Participation Local Match Minimum Local Match
85.0% 15.0% 5%

Description of Improvements

The proposed improvements include full depth reclamation of the road from existing edge of pavement to existing edge of pavement. The cross section will be constructed with a crown to direct runoff to existing storm water facilities / existing shoulders. Existing curb and gutter will be preserved. Pavement markings will be replaced in its current configuration, with two 11-foot travel lanes and intermittent parking/shoulders.