Region: Puget Sound | Legislative District: 47 | Length: 0.00 mi. | FY 2024 Arterial Preservation Program (APP) |
Existing Conditions |
TIB Funds | Local Funds | Total Costs | |
---|---|---|---|
Design | 79,943 | 14,107 | 94,050 |
Right of Way | 0 | 0 | 0 |
Construction | 612,893 | 108,157 | 721,050 |
Project Totals | $692,835 | $122,265 | $815,100 |
TIB Participation | Local Match | Minimum Local Match |
---|---|---|
85.0% | 15.0% | 15% |
This project grinds and provides a 2 inch overlay of SE 256th Street - 148th Ave SE to 156th Ave SE and upgrades 2 ADA ramps