Region: Southeast | Legislative District: 13 | Length: 0.00 mi. | FY 2024 Arterial Preservation Program (APP) |
Existing Conditions |
TIB Funds | Local Funds | Total Costs | |
---|---|---|---|
Design | 9,865 | 5,135 | 15,000 |
Right of Way | 0 | 0 | 0 |
Construction | 390,135 | 203,065 | 593,200 |
Project Totals | $400,000 | $208,200 | $608,200 |
TIB Participation | Local Match | Minimum Local Match |
---|---|---|
65.8% | 34.2% | 15% |
Pavement distress appears to be surface degradation only. Use 2 in. HMA grind and overlay to preserve pavement, and fill-in missing segment between two other recent overlay projects. City to pay for curb ramp and sidewalk replacement. Main Street - 3rd Ave to University Way