Region: Southwest | Legislative District: 20 | Length: 0.00 mi. | FY 2023 Arterial Preservation Program (APP) |
Existing Conditions |
TIB Funds | Local Funds | Total Costs | |
---|---|---|---|
Design | 57,177 | 6,353 | 63,530 |
Right of Way | 0 | 0 | 0 |
Construction | 438,327 | 48,703 | 487,030 |
Project Totals | $495,504 | $55,056 | $550,560 |
TIB Participation | Local Match | Minimum Local Match |
---|---|---|
90.0% | 10.0% | 10% |
Perform a 2-inch grind and overlay of the existing pavement, and roadway striping.