City of Chehalis
Main Street Overlay
I 5 to BNSF R/W
TIB Award Amount
$586,170
Region: Southwest   |   Legislative District: 20   |   Length: 0.00 mi. FY 2023 Arterial Preservation Program (APP)

Existing Conditions

Project Funding

  TIB Funds Local Funds Total Costs
Design 67,635 7,515 75,150
Right of Way 0 0 0
Construction 518,535 57,615 576,150
Project Totals $586,170 $65,130 $651,300

Local Match

TIB Participation Local Match Minimum Local Match
90.0% 10.0% 10%

Description of Improvements

Perform a 2-inch grind and overlay of the existing pavement, roadway striping, and replacement of existing ADA ramps.