Region: Southwest | Legislative District: 20 | Length: 0.00 mi. | FY 2023 Arterial Preservation Program (APP) |
Existing Conditions |
TIB Funds | Local Funds | Total Costs | |
---|---|---|---|
Design | 67,635 | 7,515 | 75,150 |
Right of Way | 0 | 0 | 0 |
Construction | 518,535 | 57,615 | 576,150 |
Project Totals | $586,170 | $65,130 | $651,300 |
TIB Participation | Local Match | Minimum Local Match |
---|---|---|
90.0% | 10.0% | 10% |
Perform a 2-inch grind and overlay of the existing pavement, roadway striping, and replacement of existing ADA ramps.