Region: Southeast | Legislative District: 8 | Length: 0.00 mi. | FY 2023 Arterial Preservation Program (APP) |
Existing Conditions |
TIB Funds | Local Funds | Total Costs | |
---|---|---|---|
Design | 11,659 | 2,057 | 13,716 |
Right of Way | 0 | 0 | 0 |
Construction | 184,929 | 32,634 | 217,563 |
Project Totals | $196,587 | $34,692 | $231,279 |
TIB Participation | Local Match | Minimum Local Match |
---|---|---|
85.0% | 15.0% | 15% |
Project will taper grind the existing asphalt along the gutters and overlay with 2 inches of hot mix asphalt.