Region: Puget Sound | Legislative District: 31 | Length: 0.00 mi. | FY 2022 Arterial Preservation Program (APP) |
Existing Conditions |
TIB Funds | Local Funds | Total Costs | |
---|---|---|---|
Design | 8,500 | 1,500 | 10,000 |
Right of Way | 0 | 0 | 0 |
Construction | 229,503 | 40,501 | 270,004 |
Project Totals | $238,003 | $42,001 | $280,004 |
TIB Participation | Local Match | Minimum Local Match |
---|---|---|
85.0% | 15.0% | 15% |
This project will grind and overlay the following segments: Roosevelt Avenue - 244th Avenue to Semanski Street Roosevelt Avenue - Semanski Street to Cole Street ADA ramps will be done by the city under a separate contract and are not part of this project.