Bill # Payment Date Type Predesign Spec. Study DE Engr. Right of Way CN Engr. CN Other CN Contract Total
1 03/01/2022 Payment 0.00 0.00 0.00 0.00 0.00 0.00 235,957.11 235,957.11
2 03/30/2022 Payment 0.00 0.00 0.00 0.00 0.00 0.00 202,455.74 202,455.74
3 04/22/2022 Payment 0.00 0.00 0.00 0.00 0.00 0.00 134,234.47 134,234.47
4 05/19/2022 Payment 0.00 0.00 0.00 0.00 0.00 0.00 278,139.60 278,139.60
5 06/28/2022 Payment 0.00 0.00 0.00 0.00 0.00 0.00 186,246.92 186,246.92
6 07/27/2022 Payment 0.00 0.00 0.00 0.00 0.00 0.00 126,040.13 126,040.13
7 08/29/2022 Payment 0.00 0.00 0.00 0.00 0.00 0.00 52,667.63 52,667.63
8 10/06/2022 Payment 0.00 0.00 0.00 0.00 0.00 0.00 51,998.39 51,998.39
9 10/28/2022 Payment 0.00 0.00 0.00 0.00 0.00 0.00 81,460.92 81,460.92
10 12/02/2022 Payment 0.00 0.00 0.00 0.00 7,460.52 0.00 0.00 7,460.52
11 12/27/2022 Payment 0.00 0.00 0.00 0.00 11,138.54 0.00 0.00 11,138.54
12 01/23/2023 Payment 0.00 0.00 0.00 0.00 0.00 0.00 10,006.23 10,006.23
13 02/28/2023 Payment 0.00 0.00 0.00 0.00 0.00 0.00 2,562.76 2,562.76
14 03/27/2023 Payment 0.00 0.00 0.00 0.00 0.00 0.00 3,653.81 3,653.81
15 05/15/2023 Payment 0.00 0.00 0.00 0.00 0.00 0.00 42,922.13 42,922.13
16 06/30/2023 Payment 0.00 0.00 0.00 0.00 0.00 0.00 21,645.49 21,645.49
17 07/27/2023 Payment 0.00 0.00 0.00 0.00 0.00 0.00 7,980.22 7,980.22
18 09/15/2023 Payment 0.00 0.00 0.00 0.00 91,809.12 0.00 0.00 91,809.12
19 10/02/2023 Payment 0.00 0.00 0.00 0.00 -110,408.18 0.00 133,814.43 23,406.25
20 10/26/2023 Payment 0.00 0.00 0.00 0.00 142,393.27 0.00 13,408.41 155,801.68
21 11/27/2023 Payment 0.00 0.00 0.00 0.00 30,319.65 0.00 44,261.11 74,580.76
22 03/08/2024 Payment 0.00 0.00 0.00 0.00 11,053.27 0.00 31,453.69 42,506.96
TOTAL PAYMENTS 0.00 0.00 0.00 0.00 183,766.19 0.00 1,660,909.19 1,844,675.38