Transportation Improvement Board
Performance Management Dashboard

 Projects — TIB Project Information

TIB Project Information

City of Woodland's LED Streetlight Conversion

S-W-954(001)-1

S-W-954(001)-1
LED Streetlight Conversion

PUD Owned

FY 2024 LED Program
Current Phase : Audit
Total TIB Funding : $40,000

County: Cowlitz/Clark   |   Legislative District: 20   |   Project Length: 0.10   |   TIB Engineer: Chris Langhoff   |   Last Payment Date: 10/31/2023

Project Information

Lead Agency WOODLAND
Funding Year 2024
Program LED
Current Phase Audit
Legislative District 20
Congressional District 3
Federal Route Number 9999
Project Length 0.10 mi.
ADT 0
Functional Class TIB Arterial
Type of Work
Project Contact Tracy Coleman
Contact Email colemant@ci.woodland.wa.us
TIB Engineer Chris Langhoff
Last Payment Date 10/31/2023
Cultural Resource Assessment Not Required

Project Schedule

  Target Date Actual Date
Project Selection Date   12/27/2022
Delayed Project Date 07/01/2025  
DAHP Assessment Date  
Predesign Approval
Design Approval 05/01/2023 06/12/2023
Bid Auth. Approval 05/01/2023 06/12/2023
Construction Approval 05/01/2023 06/12/2023
Project Closeout 12/31/2023 10/13/2023
Audit Date   10/31/2023
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 0 0
Right of Way 0 0
Total Design 0 0
     
Construction Engineering 0 0
Construction Contract 40,000 40,000
Other Construction 0 0
Total Construction 40,000 40,000
     
Total TIB Funding 40,000 40,000

Local Funding Partners

Funding Amount Percent
WOODLAND 0 0.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 0 0.0%

Project Description

The city will replace 148 HPS lights with LED street lights.

Project Pictures

No images available.

Project Delays

Delay Type Resolution Date Comments

No delayed project history.