McBryde Avenue is a primary pedestrian corridor for the north side of the City. This corridor has pedestrian facilities west of Church Street to link the northwest side of town to the high school but has no facilities or inadequate facilities to serve the northeast areas of the City. The existing McBryde Avenue corridor west of Church Street is very narrow with a 10 foot asphalt lanes and limited shoulder width in many locations. It is very common to encounter pedestrians walking in the narrow roadway. The City of Montesano is a very active community. In addition to the need for safe pedestrian facilities to serve the high school, many residents use McBryde Avenue regularly as a walking corridor throughout the day. The City completed 650 feet of new sidewalk on the west end of the corridor using TIB funding in 2022 and will finish a 700 foot section on the east end in the fall of 2022 using City funds. There is still a 1,500 gap between the two sections.
Projects — TIB Project Information
TIB Project Information
City of Montesano's McBryde Avenue Sidewalk Phase 3
P-W-957(P03)-1
P-W-957(P03)-1
McBryde Avenue Sidewalk Phase 3
Calder ROW to Satsop St
FY 2024 Active Transportation Program
Current Phase : Audit
Total TIB Funding : $222,770
County: Grays Harbor | Legislative District: 19 | Project Length: 650.00 | TIB Engineer: Chris Langhoff | Last Payment Date: 10/31/2023
Project Information
Lead Agency | MONTESANO |
Funding Year | 2024 |
Program | ATP |
Current Phase | Audit |
Legislative District | 19 |
Congressional District | 6 |
Federal Route Number | 9999 |
Project Length | 650.00 mi. |
ADT | 500 |
Functional Class | TIB Arterial |
Type of Work | Pedestrian |
Project Contact | Mike Olden |
Contact Email | molden@montesano.us |
TIB Engineer | Chris Langhoff |
Last Payment Date | 10/31/2023 |
Cultural Resource Assessment | CRA |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 12/02/2022 | |
Delayed Project Date | 01/01/2024 | |
DAHP Assessment Date | ||
Predesign Approval | ||
Design Approval | 02/01/2023 | 01/09/2023 |
Bid Auth. Approval | 06/30/2023 | 07/20/2023 |
Construction Approval | 08/20/2023 | 08/08/2023 |
Project Closeout | 10/30/2023 | 10/18/2023 |
Audit Date | 10/31/2023 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 0 | 0 |
Right of Way | 0 | 0 |
Total Design | 0 | 0 |
Construction Engineering | 0 | 0 |
Construction Contract | 188,000 | 234,495 |
Other Construction | 0 | 0 |
Total Construction | 188,000 | 234,495 |
Funding Increase | 50,000 | |
Funding Surplus | - 15,230 | |
Total TIB Funding | 222,770 | 234,495 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
MONTESANO | 11,725 | 5.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 11,725 | 5.0% |
Project Description
Installing another 650 feet of sidewalk from the Calder right of way to Satsop Street. Complete the storm water and the remaining 750 feet of sidewalk work to east of Satsop Street with City funding and City labor.
Existing Condition
Project Benefits
- Improves pedestrian safety;
- Removes ADA barriers
Project Pictures
No images available.
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |