This project will replace the current sidewalks along Railroad Avenue between 8th Street and 12th Street. The existing sidewalks are discontinuous, narrow and in poor repair. Significant gaps exist in the ADA accessibility between residential areas and the central business district. Several of the missing ADA facilities also impair access to Evergreen Elementary School. Several areas along the sidewalks are at or below surrounding grade which results in the water ponding on the pedestrian path. Multiple people park their vehicles on the sidewalk, preventing pedestrians from accessing the sidewalk and forcing pedestrians to walk in the street to get around the vehicle.
Projects — TIB Project Information
TIB Project Information
City of Shelton's Railroad Avenue
P-W-194(P01)-1
P-W-194(P01)-1
Railroad Avenue
8th Street to City Limits
FY 2020 Sidewalk Program
Current Phase : Audit
Total TIB Funding : $370,010
County: Mason | Legislative District: 35 | Project Length: 0.56 | TIB Engineer: Chris Langhoff | Last Payment Date: 08/14/2023
Project Information
Lead Agency | SHELTON |
Funding Year | 2020 |
Program | SP |
Current Phase | Audit |
Legislative District | 35 |
Congressional District | 10 |
Federal Route Number | 5460 |
Project Length | 0.56 mi. |
ADT | 6,348 |
Functional Class | Principal |
Type of Work | Pedestrian |
Project Contact | Craig Gregory |
Contact Email | craig@ci.shelton.wa.us |
TIB Engineer | Chris Langhoff |
Last Payment Date | 08/14/2023 |
Cultural Resource Assessment | CRA |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/16/2018 | |
Delayed Project Date | 07/01/2021 | |
DAHP Assessment Date | ||
Predesign Approval | ||
Design Approval | 01/01/2019 | 12/26/2018 |
Bid Auth. Approval | 02/01/2022 | 01/28/2022 |
Construction Approval | 04/01/2022 | 03/11/2022 |
Project Closeout | 07/31/2023 | 08/02/2023 |
Audit Date | 08/14/2023 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 0 | 152,526 |
Right of Way | 0 | 0 |
Total Design | 0 | 152,526 |
Construction Engineering | 0 | 203,514 |
Construction Contract | 350,000 | 1,232,359 |
Other Construction | 0 | 0 |
Total Construction | 350,000 | 1,435,873 |
Funding Increase | 20,010 | |
Total TIB Funding | 370,010 | 1,588,399 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
SHELTON | 1,218,389 | 76.7% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 1,218,389 | 76.7% |
Project Description
The project establishes continuous ADA accessibility and new sidewalks from the west city limits to the central business district. The existing sidewalks on the south side of Railroad Ave., between 8th and 12th Streets, will be removed and replaced with new 8-foot sidewalks and ADA compliant curb ramps will be installed at each intersection. On the north side of Railroad Ave. between 10th and 12th St. new 8-foot sidewalks will be installed. The new sidewalks will be raised 6-inches above existing grade to promote stormwater runoff as well as prevent vehicles from parking on the sidewalk and obstructing sidewalk access. The crossing at the existing railroad tracks will be designed to provide an at grade pedestrian crossing. The existing sidewalk west of 12th St. will be removed, raised 6-inches above existing grade, and replaced to the city limits. All new sidewalks will be separated from the roadway by a width of at least 4-feet. New driveways will be installed to allow resident and business access. Existing roadway regulatory signs will be removed and replaced to improve pedestrian safety.
Existing Condition
Project Benefits
- Improves pedestrian safety;
- Removes ADA barriers;
- Builds multimodal facilities
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |