Multiple sidewalk gaps exist around the City. Gaps are primarily located in between recent or new developments on parcels that are not anticipated to develop in the new future. The community needs these gaps filled to provide contiguous sidewalk routes for pedestrian access.
Projects — TIB Project Information
TIB Project Information
City of Enumclaw's In Fill Sidewalk
P-P-124(P03)-1
P-P-124(P03)-1
In Fill Sidewalk
Various gaps
FY 2024 Active Transportation Program
Current Phase : Construction
Total TIB Funding : $380,504
County: King | Legislative District: 31 | Project Length: 0.25 | TIB Engineer: Greg Armstrong | Last Payment Date:
Project Information
Lead Agency | ENUMCLAW |
Funding Year | 2024 |
Program | ATP |
Current Phase | Construction |
Legislative District | 31 |
Congressional District | 8 |
Federal Route Number | 8000 |
Project Length | 0.25 mi. |
ADT | 550 |
Functional Class | Minor |
Type of Work | Pedestrian |
Project Contact | Lance Talmadge |
Contact Email | ltalmadge@ci.enumclaw.wa.us |
TIB Engineer | Greg Armstrong |
Last Payment Date | |
Cultural Resource Assessment | CRA & BER |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 12/02/2022 | |
Delayed Project Date | 01/01/2024 | |
DAHP Assessment Date | 06/01/2023 | |
Predesign Approval | ||
Design Approval | 01/01/2023 | 01/10/2023 |
Bid Auth. Approval | 09/30/2023 | 09/18/2023 |
Construction Approval | 10/31/2023 | 10/30/2023 |
Project Closeout | 06/30/2024 | |
Audit Date | ||
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 0 | 0 |
Right of Way | 0 | 0 |
Total Design | 0 | 0 |
Construction Engineering | 32,300 | 16,820 |
Construction Contract | 298,204 | 487,803 |
Other Construction | 0 | 0 |
Total Construction | 330,504 | 504,623 |
Funding Increase | 50,000 | |
Total TIB Funding | 380,504 | 504,623 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
ENUMCLAW | 124,119 | 24.6% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 124,119 | 24.6% |
Project Description
The project will fill five gaps in the Enumclaw sidewalk system.
Existing Condition
Project Benefits
- Improves pedestrian safety;
- Completes gap;
- Removes ADA barriers
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |