The parcel at 11635 NE 8th Street is missing approximately 150 feet of even, ADA grade accessible sidewalk on the south side NE 8th Street, an 8-lane arterial roadway. Pedestrian commuters and travelers must cross this gap to access downtown Bellevue, transit, medical facilities, local destinations, the Wilburton station of the new Sound Transit East Link light rail line (open 2023), and the grade separated Eastrail Regional Trail crossing of NE 8th Street (currently under construction immediately to the east (also open 2023). Pedestrians experience an unmarked and uneven surface that is periodically blocked by light standards when traveling on the south side of the street between 116th and 120th Avenues NE. Also, pedestrians are not easily visible to vehicles entering and exiting the retail parking lot housed on this parcel.
Projects — TIB Project Information
TIB Project Information
City of Bellevue's NE 8th Street
P-P-103(P04)-1
P-P-103(P04)-1
NE 8th Street
Parcel Frontage at 11635 NE 8th St
FY 2023 Sidewalk Program
Current Phase : Withdrawn
Total TIB Funding : $32,990
County: King | Legislative District: 48 | Project Length: 0.03 | TIB Engineer: Greg Armstrong | Last Payment Date: 03/27/2024
Project Information
Lead Agency | BELLEVUE |
Funding Year | 2023 |
Program | SP |
Current Phase | Withdrawn |
Legislative District | 48, 41 |
Congressional District | 9 |
Federal Route Number | 2040 |
Project Length | 0.03 mi. |
ADT | 35,600 |
Functional Class | Principal |
Type of Work | Pedestrian |
Project Contact | Mia Waters |
Contact Email | mwaters@bellevuewa.gov |
TIB Engineer | Greg Armstrong |
Last Payment Date | 03/27/2024 |
Cultural Resource Assessment | Not Required |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/19/2021 | |
Delayed Project Date | 07/01/2024 | |
DAHP Assessment Date | ||
Predesign Approval | ||
Design Approval | 03/01/2022 | 02/22/2022 |
Bid Auth. Approval | 03/31/2024 | |
Construction Approval | 04/15/2024 | |
Project Closeout | 12/31/2024 | |
Audit Date | ||
Withdrawn Date | 04/02/2024 |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 32,990 | 50,975 |
Right of Way | 0 | 0 |
Total Design | 32,990 | 50,975 |
Construction Engineering | 0 | 0 |
Construction Contract | 0 | 0 |
Other Construction | 0 | 0 |
Total Construction | 0 | 0 |
Total TIB Funding | 32,990 | 50,975 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
BELLEVUE | 17,985 | 35.3% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 17,985 | 35.3% |
Project Description
This project will fill the sidewalk gap by constructing approximately 150 feet of 8-ft wide, ADA accessible sidewalk along the frontage of the parcal at 11635 NE 8th Street.
Existing Condition
Project Benefits
- Improves pedestrian safety;
- Completes gap;
- Removes ADA barriers
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |