 Projects — TIB Project Information

TIB Project Information

City of Tieton's Franklin Road

P-E-945(P02)-1

P-E-945(P02)-1
Franklin Road

North Fork Cowiche Creek

FY 2021 Sidewalk Program
Current Phase : Audit
Total TIB Funding : $174,333

County: Yakima   |   Legislative District: 14   |   Project Length: 0.01   |   TIB Engineer: Jonathan Heusman   |   Last Payment Date: 04/17/2023

Project Information

Lead Agency TIETON
Funding Year 2021
Program SP
Current Phase Audit
Legislative District 14
Congressional District 4
Federal Route Number 9999
Project Length 0.01 mi.
ADT 770
Functional Class TIB Arterial
Type of Work Pedestrian
Project Contact Frank Brewer
Contact Email mhtieton@centurytel.net
TIB Engineer Jonathan Heusman
Last Payment Date 04/17/2023
Cultural Resource Assessment CRA

Project Schedule

  Target Date Actual Date
Project Selection Date   11/22/2019
Delayed Project Date 07/01/2022  
DAHP Assessment Date   01/23/2020
Predesign Approval
Design Approval 02/01/2020 12/30/2019
Bid Auth. Approval 10/31/2021 12/21/2021
Construction Approval 01/15/2022 01/11/2021
Project Closeout 04/30/2023 04/18/2023
Audit Date   04/17/2023
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 18,810 18,810
Right of Way 0 0
Total Design 18,810 18,810
     
Construction Engineering 18,810 31,310
Construction Contract 125,400 169,199
Other Construction 0 0
Total Construction 144,210 200,509
     
Funding Increase 11,313  
Total TIB Funding 174,333 219,319

Local Funding Partners

Funding Amount Percent
TIETON 44,986 20.5%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 44,986 20.5%

Project Description

In 2019 Tieton was awarded $300,000 in Complete Streets funding to design and construct continuation of sidewalk and curb and gutter from Arkansas Avenue northerly on Franklin Road (east side) towards the North Fork of Cowiche Creek. Environmental documentation and permitting for the Franklin Road pedestrian bridge was included in the Complete Streets funding Work Plan. To complete the identified Franklin Road non-motorized corridor, the City needs to design and construct the pedestrian bridge across the North Fork of Cowiche Creek.

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments