Warren Avenue between Chris St and Riverside Drive provides a pathway from the K 12 school campus to the sports complex. There is currently no sidewalk along this portion of the route and students must walk along the shoulder of the roadway. The width of the roadway promotes higher traffic speeds and there is currently no accessible route between the school and downtown area to the sports courts/park/beach/kayak launch area.
Projects — TIB Project Information
TIB Project Information
City of Pateros's Warren Avenue
P-E-883(P04)-1
P-E-883(P04)-1
Warren Avenue
Riverside Dr to Chris St
FY 2021 Sidewalk Program
Current Phase : Audit
Total TIB Funding : $479,458
County: Okanogan | Legislative District: 12 | Project Length: 0.28 | TIB Engineer: Andrew Beagle | Last Payment Date: 03/15/2023
Project Information
Lead Agency | PATEROS |
Funding Year | 2021 |
Program | SP |
Current Phase | Audit |
Legislative District | 12 |
Congressional District | 4 |
Federal Route Number | 9999 |
Project Length | 0.28 mi. |
ADT | 300 |
Functional Class | TIB Arterial |
Type of Work | Pedestrian |
Project Contact | Jord Wilson |
Contact Email | paterosparks@outlook.com |
TIB Engineer | Andrew Beagle |
Last Payment Date | 03/15/2023 |
Cultural Resource Assessment | CRA |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/22/2019 | |
Delayed Project Date | 07/01/2022 | |
DAHP Assessment Date | 01/28/2021 | |
Predesign Approval | ||
Design Approval | 02/01/2020 | 01/29/2020 |
Bid Auth. Approval | 04/01/2021 | 06/07/2021 |
Construction Approval | 03/01/2022 | 03/30/2022 |
Project Closeout | 02/20/2023 | 02/27/2023 |
Audit Date | 03/15/2023 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 46,039 | 46,716 |
Right of Way | 0 | 0 |
Total Design | 46,039 | 46,716 |
Construction Engineering | 46,039 | 72,980 |
Construction Contract | 306,928 | 368,814 |
Other Construction | 0 | 0 |
Total Construction | 352,967 | 441,794 |
Funding Increase | 80,452 | |
Total TIB Funding | 479,458 | 488,510 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
PATEROS | 9,052 | 1.9% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 9,052 | 1.9% |
Project Description
The project proposes construction of curb, sidewalk, and curb ramps. Project will connect to the sidewalk constructed under Phase II, west of Chris St and terminate at the sports courts/park/beach/kayak launch area. The project will include three crosswalks including ADA compliant ramps. Roadway will be narrowed as a traffic calming measure to reduce speeds and promote safety. A pedestrian buffer will also be incorporated to add to increased safety to students, residents and pedestrians. Warren Ave is the primary arterial west of SR-97. The sidewalk constructed along Warren Ave during the previous phases connect this arterial to the commercial district and to the school. This final phase will provide a safe and accessible route for students pedestrians along the full length of Warren Ave.
Existing Condition
Project Benefits
- Improves pedestrian safety;
- Completes gap;
- Removes ADA barriers
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |