City of Selah's Valleyview Avenue / Third Street / Southern Avenue

P-E-182(P03)-1

P-E-182(P03)-1
Valleyview Avenue / Third Street / Southern Avenue

S First Ave to S First Ave

FY 2023 Sidewalk Program
Current Phase : Audit
Total TIB Funding : $272,607

County: Yakima   |   Legislative District: 15   |   Project Length: 0.64   |   TIB Engineer: Jonathan Heusman   |   Last Payment Date: 10/31/2023

Project Information

Lead Agency SELAH
Funding Year 2023
Program SP
Current Phase Audit
Legislative District 15
Congressional District 4
Federal Route Number 4709
Project Length 0.64 mi.
ADT 2,050
Functional Class Collector
Type of Work Pedestrian
Project Contact Rocky Wallace
Contact Email rocky.wallace@selahwa.gov
TIB Engineer Jonathan Heusman
Last Payment Date 10/31/2023
Cultural Resource Assessment Not Required

Project Schedule

  Target Date Actual Date
Project Selection Date   11/19/2021
Delayed Project Date 01/01/2023  
DAHP Assessment Date  
Predesign Approval
Design Approval 02/01/2022 12/22/2021
Bid Auth. Approval 11/15/2022 11/21/2022
Construction Approval 01/15/2023 01/30/2023
Project Closeout 12/31/2023 10/31/2023
Audit Date   10/31/2023
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 0 0
Right of Way 0 0
Total Design 0 0
     
Construction Engineering 52,188 272,607
Construction Contract 347,812 657,054
Other Construction 0 0
Total Construction 400,000 929,661
     
Funding Surplus - 127,393  
Total TIB Funding 272,607 929,661

Local Funding Partners

Funding Amount Percent
SELAH 0 0.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
Federal Funding  657,054 70.7%
Total Local Funding 657,054 70.7%

Project Description

Reconstruction of Valleyview Avenue, Third Street, and Southern Avenue to a 28-foot wide, two-lane roadways. The project will include curb and gutters, sidewalks, intersection curb ramps, storm drainage facilities, and illumination system.

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments