Abbott Road provides direct access to Walla Wallas public high school, Wa-Hi, and lacks contiguous pedestrian improvements within project limits Abbott Rd has sidewalk on only the south side of the road. Abbott Road also provides direct access to Murr Field, which includes sports fields and a walking path. Student drop-off and transit access to Wa-Hi are located on Abbott Road. This area experiences high levels of congestion and has an APMVM over 17. A school bond was approved in 2018 improvements funded by that bond include revising the existing student drop-off area on the south side of Abbott Rd, including parking, sidewalks, bulb-outs, and crossings.Part of Abbott Road is under the city jurisdiction, and the citys identified the Abbott Road/Fern Avenue intersection as the third highest intersection safety concern in the city. Walla Walla Public Schools, the county and the city are collaborating to improve safety.
Projects — TIB Project Information
TIB Project Information
Walla Walla County's Abbott Road
P-E-036(P02)-1
P-E-036(P02)-1
Abbott Road
Scarpelli Dr to Fern Ave
FY 2021 Sidewalk Program
Current Phase : Audit
Total TIB Funding : $142,974
County: Walla Walla | Legislative District: 16 | Project Length: 0.21 | TIB Engineer: Jonathan Heusman | Last Payment Date: 07/17/2023
Project Information
Lead Agency | WALLA WALLA COUNTY |
Funding Year | 2021 |
Program | SP |
Current Phase | Audit |
Legislative District | 16 |
Congressional District | 5 |
Federal Route Number | 7158 |
Project Length | 0.21 mi. |
ADT | 1,408 |
Functional Class | Collector |
Type of Work | Pedestrian |
Project Contact | Seth Walker |
Contact Email | swalker@wwcountyroads.com |
TIB Engineer | Jonathan Heusman |
Last Payment Date | 07/17/2023 |
Cultural Resource Assessment | CRA |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/22/2019 | |
Delayed Project Date | 07/01/2022 | |
DAHP Assessment Date | ||
Predesign Approval | ||
Design Approval | 02/01/2020 | 01/21/2020 |
Bid Auth. Approval | 06/10/2022 | 06/29/2022 |
Construction Approval | 07/30/2022 | 07/27/2022 |
Project Closeout | 08/31/2023 | 07/11/2023 |
Audit Date | 07/17/2023 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 12,182 | 56,108 |
Right of Way | 0 | 0 |
Total Design | 12,182 | 56,108 |
Construction Engineering | 9,746 | 69,477 |
Construction Contract | 76,023 | 418,904 |
Other Construction | 37,549 | 0 |
Total Construction | 123,318 | 488,381 |
Funding Increase | 7,474 | |
Total TIB Funding | 142,974 | 544,489 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
WALLA WALLA COUNTY | 360,050 | 66.1% |
WSDOT Funding | 0 | 0.0% |
School District | 34,595 | 6.4% |
City of Walla Walla | 6,869 | 1.3% |
Total Local Funding | 401,515 | 73.8% |
Project Description
Walla Walla County proposes to construct 6-foot wide curb, gutter, and sidewalk on the north side of Abbott Road between Scarpelli Street and existing sidewalk past the curb return at the intersection of Abbott Road and Fern Avenue. Walla Walla Public Schools will construct bulb-outs and ADA ramps at the intersection of Scarpelli Drive and Abbott Road, and at any additional crossings within project limits. Further, Walla Walla Public Schools, Walla Walla County, and the City of Walla Walla are collaborating to determine the best measures to improve safety at the Abbott Road/Fern Avenue intersection, to be completed at a later date, outside the scope of this project. Those measures will address, at a minimum, fully accessible crossings and improved sight distance, and may include solutions such as a mini-roundabout.
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |