Projects — TIB Project Information
TIB Project Information
City of Castle Rock's Complete Streets Award
C-W-952(001)-1
C-W-952(001)-1
Complete Streets Award
March 2019 Selection
FY 2020 Complete Streets Program
Current Phase : Audit
Total TIB Funding : $200,000
County: Cowlitz | Legislative District: 20 | Project Length: 0.10 | TIB Engineer: Chris Langhoff | Last Payment Date: 05/02/2019
Project Information
Lead Agency | CASTLE ROCK |
Funding Year | 2020 |
Program | CSP |
Current Phase | Audit |
Legislative District | 20 |
Congressional District | 3 |
Federal Route Number | 9999 |
Project Length | 0.10 mi. |
ADT | 0 |
Functional Class | Local Access |
Type of Work | Pedestrian |
Project Contact | David Vorse |
Contact Email | crpwd@ci.castle-rock.wa.us |
TIB Engineer | Chris Langhoff |
Last Payment Date | 05/02/2019 |
Cultural Resource Assessment |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 03/28/2019 | |
Delayed Project Date | 07/01/2021 | |
DAHP Assessment Date | ||
Predesign Approval | ||
Design Approval | 05/01/2019 | |
Bid Auth. Approval | 05/01/2019 | |
Construction Approval | 04/22/2019 | 04/22/2019 |
Project Closeout | 12/31/2021 | 03/30/2023 |
Audit Date | 03/30/2023 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 0 | 0 |
Right of Way | 0 | 0 |
Total Design | 0 | 0 |
Construction Engineering | 0 | 0 |
Construction Contract | 200,000 | 200,000 |
Other Construction | 0 | 0 |
Total Construction | 200,000 | 200,000 |
Total TIB Funding | 200,000 | 200,000 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
CASTLE ROCK | 0 | 0.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 0 | 0.0% |
Complete Streets Workplan
Item | Type of Work | Date Added | Est. Cost | Actual Cost | Complete |
---|---|---|---|---|---|
Construct pedestrian relief island on SB ramp to I-5 at exit 49, west side |
Pedestrian | Mar 2019 | $37,000 | $ 0 | |
Provide alignment of crosswalk with pedstrian safety | |||||
Re-align crosswalks on west side of I-5 to be pedestrian / bike friendly |
Pedestrian; Bicycle | Mar 2019 | $10,000 | $ 0 | |
Pavement markings at SB I-5 ramp - 900 sq.ft. | |||||
Construct 200 feet of shared use path from SB ramp (SR 411) south side |
Pedestrian; Bicycle | Mar 2019 | $25,000 | $18,407 | |
10 foot by 4 inch thick concrete shared use path with ADA ramps bewtween SB ramp to driveway in ROW | |||||
Traffic mangement of existing shoulder on SR 411 | Pedestrian; Bicycle | Mar 2019 | $10,000 | $39,757 | |
Reduce lanes to 11' wide | |||||
Replace 34 ADA ramps constructed in the 1970's -90's to current code |
Pedestrian | Mar 2019 | $110,000 | $112,712 | |
Located on Cowlitz, A, B and C Streets; and Leaming, 1st, 2nd, 3rd and 4th. | |||||
Replace 80 feet of broken up sidewalk on Cowlitz St. East, 100 block |
Pedestrian | Mar 2019 | $13,000 | $3,534 | |
100 Block of Cowlitz Street East from Huntington Ave. east toward Kirby Ave. SE (both are arterial streets) | |||||
Install pedestrian friendly lighting along ped. corrider/widen shoulder on Huntington Ave. |
Pedestrian; Bicycle | Jun 2020 | $42,000 | $104,402 | |
Provide pedestrian safety lighting for pedestrian corridor |
Project Pictures
No images available.
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |