TIB Project Information

City of Kent's Complete Streets Award

C-P-106(003)-1

C-P-106(003)-1
Complete Streets Award

March 2022 Selection

FY 2023 Complete Streets Program
Current Phase : Audit
Total TIB Funding : $750,000

County: King   |   Legislative District: 33   |   Project Length: 0.00   |   TIB Engineer: Greg Armstrong   |   Last Payment Date: 06/07/2022

Project Information

Lead Agency KENT
Funding Year 2023
Program CSP
Current Phase Audit
Legislative District 33
Congressional District 9
Federal Route Number 1224
Project Length 0.00 mi.
ADT 4,100
Functional Class Collector
Type of Work Pedestrian
Project Contact Rob Brown
Contact Email RBrown@kentwa.gov
TIB Engineer Greg Armstrong
Last Payment Date 06/07/2022
Cultural Resource Assessment

Project Schedule

  Target Date Actual Date
Project Selection Date   03/28/2022
Delayed Project Date 03/28/2025  
DAHP Assessment Date  
Predesign Approval
Design Approval 05/01/2022
Bid Auth. Approval 05/01/2022
Construction Approval 05/05/2022 05/23/2022
Project Closeout 12/31/2023 11/21/2023
Audit Date   11/21/2023
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 0 0
Right of Way 0 0
Total Design 0 0
     
Construction Engineering 0 0
Construction Contract 750,000 750,000
Other Construction 0 0
Total Construction 750,000 750,000
     
Total TIB Funding 750,000 750,000

Local Funding Partners

Funding Amount Percent
KENT 0 0.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 0 0.0%

Complete Streets Workplan

Item Type of Work Date Added Est. Cost Actual Cost Complete
Russell Road Non-Motorized Mar 2022 $750,000 $839,532
Complete a non-motorized gap between Hogan Park, the Meeker Street residential/commercial area and the Green River Trail connector near low-income housing, Includes B-ft sidewalk, street trees and ped lighting on the east side, with a bikeable shoulder on the west side. Speed cushions will be installed to reduce speeds.

Project Pictures

No images available.

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments