Center Parkway will be an extension of the existing roadway crossing several sets of railroad tracks.
Projects — TIB Project Information
TIB Project Information
City of Richland's Gage Blvd/Center Parkway
9-E-171(003)-3
9-E-171(003)-3
Gage Blvd/Center Parkway
Gage Blvd to Tapteal Dr
FY 2007 Urban Corridor Program
Current Phase : Construction
Total TIB Funding : $644,320
County: Benton | Legislative District: 8 | Project Length: 0.30 | TIB Engineer: Jonathan Heusman | Last Payment Date: 12/06/2022
Project Information
Lead Agency | RICHLAND |
Funding Year | 2007 |
Program | UCP |
Current Phase | Construction |
Legislative District | 8 |
Congressional District | 4 |
Federal Route Number | 3459 |
Project Length | 0.30 mi. |
ADT | 0 |
Functional Class | Minor |
Type of Work | New Location |
Project Contact | Pete Rogalsky |
Contact Email | progalsky@ci.richland.wa.us |
TIB Engineer | Jonathan Heusman |
Last Payment Date | 12/06/2022 |
Cultural Resource Assessment | Section 106 |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/18/2005 | |
Delayed Project Date | 07/01/2011 | |
DAHP Assessment Date | 05/23/2022 | |
Predesign Approval | ||
Design Approval | 06/01/2006 | 04/14/2006 |
Bid Auth. Approval | 12/01/2015 | 05/23/2022 |
Construction Approval | 07/22/2022 | 07/21/2022 |
Project Closeout | 03/31/2024 | |
Audit Date | ||
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 344,320 | 2,782,200 |
Right of Way | 300,000 | 2,628,500 |
Total Design | 644,320 | 5,410,700 |
Construction Engineering | 0 | 156,253 |
Construction Contract | 0 | 1,754,688 |
Other Construction | 0 | 0 |
Total Construction | 0 | 1,910,941 |
Total TIB Funding | 644,320 | 7,321,641 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
RICHLAND | 1,247,989 | 17.0% |
WSDOT Funding | 0 | 0.0% |
STP Direct | 882,300 | 12.1% |
Port of Kennewick | 400,000 | 5.5% |
Port of Benton | 50,000 | 0.7% |
Benton County | 2,996,611 | 40.9% |
City of Kennewick | 1,100,421 | 15.0% |
Total Local Funding | 6,677,321 | 91.2% |
Project Description
The construction of Center Parkway will include four travel lanes. There will be a bicycle lane and a sidewalk with curb and gutter on both sides of the roadway. There will be a new at grade railroad crossing with vehicular and pedestrian crossing gates. The storm water drainage system will be constructed and illumination will be added as required.
Existing Condition
Project Benefits
- Improves Non-Motorized Usage;
- Promotes Economic Growth;
- Increases Mobility
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
Coordination Issues Level 2 Board Delay |
06/27/2022 | The City of Kennewick has given up trying to gain approval for an additional at-grade crossing from the railroad. The City of Richland is still pursuing an agreement with the railroad. Hopes appear doubtful and this project is likely to be withdrawn. |