The Stage 1 and Stage 2 project limits are 1.62 mi. BST & HMA-paved minor arterial has two 11-12 ft. lanes, with 8-9 ft. paved or 2-5 ft. unpaved shoulders and a 1025 ft left turn lane zone at S. 42nd Ave. All intersections are 'stop controlled at minor approaches' with no signalization nor illumination. Ahtanum Rd. is a T-2 Truck, Class-1 Bicycle, and Ped./Tourist Route, serving properties south of the Yakima Airport. The city owned 16th Ave. to City Limits section is a 4-lane w/ bike lane configuration that tapers to a two lane alignment. ADT's range from 8,872 (at S. 26th Ave) to 7,226 (at S. 52nd Ave) with a 25-30% projected increase following construction completion of a $40M, 500k sqft. fruit packing facility near 16th Ave., and a $14M, 19-field soccer/athletic center complex off of S. 38th Ave. Since 2002, 74 accidents, including two pedestrian fatality and 24 injury accidents (32 total injuries) have occurred w/in project area.
Projects — TIB Project Information
TIB Project Information
Yakima County's Ahtanum Road
8-4-039(026)-2
8-4-039(026)-2
Ahtanum Road
Yakima C/L to S 52nd Ave
FY 2018 Urban Arterial Program
Current Phase : Construction
Total TIB Funding : $0
County: Yakima | Legislative District: 14 | Project Length: 1.62 | TIB Engineer: Jonathan Heusman | Last Payment Date:
Project Information
Lead Agency | YAKIMA COUNTY |
Funding Year | 2018 |
Program | UAP |
Current Phase | Construction |
Legislative District | 14, 15 |
Congressional District | 4 |
Federal Route Number | 4550 |
Project Length | 1.62 mi. |
ADT | 0 |
Functional Class | Minor |
Type of Work | Major Widening |
Project Contact | Matt Pietrusiewicz, P.E. |
Contact Email | Matt.Pietrusiewicz@co.yakima.wa.us |
TIB Engineer | Jonathan Heusman |
Last Payment Date | |
Cultural Resource Assessment | CRA |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/18/2016 | |
Delayed Project Date | 07/01/2021 | |
DAHP Assessment Date | 08/07/2020 | |
Predesign Approval | ||
Design Approval | 01/01/2017 | 12/27/2016 |
Bid Auth. Approval | 03/31/2022 | 04/27/2022 |
Construction Approval | 06/15/2022 | 07/13/2022 |
Project Closeout | 09/27/2024 | |
Audit Date | ||
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 0 | 0 |
Right of Way | 0 | 0 |
Total Design | 0 | 0 |
Construction Engineering | 0 | 300,000 |
Construction Contract | 0 | 3,514,062 |
Other Construction | 0 | 0 |
Total Construction | 0 | 3,814,062 |
Total TIB Funding | 0 | 3,814,062 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
YAKIMA COUNTY | 3,814,062 | 100.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 3,814,062 | 100.0% |
Project Description
This project Stage will reconstruct 0.80 miles of roadway to a standard three-lane urban arterial section, with 12-foot through lanes and an 11-foot two-way left-turn lane, curbing with a variable width swale (2-9 feet), a 10-foot shared use asphalt pathway, roadside illumination, improved signage and clear zones, and a three-leg signal system at the intersection of Ahtanum Road and 52nd Avenue.
Existing Condition
Project Benefits
- Improves safety;
- Supports economic development;
- Extends improvements
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |