City of Spokane Valley's Broadway Avenue Concrete Intersection

8-3-208(013)-1

8-3-208(013)-1
Broadway Avenue Concrete Intersection

Park Rd

FY 2024 Urban Arterial Program
Current Phase : Construction
Total TIB Funding : $1,655,420

County: Spokane   |   Legislative District: 4   |   Project Length: 0.08   |   TIB Engineer: Andrew Beagle   |   Last Payment Date: 02/12/2024

Project Information

Lead Agency SPOKANE VALLEY
Funding Year 2024
Program UAP
Current Phase Construction
Legislative District 4
Congressional District 5
Federal Route Number 3846
Project Length 0.08 mi.
ADT 16,500
Functional Class Minor
Type of Work Reconstruction
Project Contact Robert Lochmiller
Contact Email rlochmiller@spokanevalley.org
TIB Engineer Andrew Beagle
Last Payment Date 02/12/2024
Cultural Resource Assessment Not Required

Project Schedule

  Target Date Actual Date
Project Selection Date   12/02/2022
Delayed Project Date 07/01/2027  
DAHP Assessment Date  
Predesign Approval
Design Approval 02/01/2023 12/15/2022
Bid Auth. Approval 04/15/2023 04/24/2023
Construction Approval 05/15/2023 05/22/2023
Project Closeout 06/30/2024
Audit Date  
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 75,502 70,000
Right of Way 0 60,000
Total Design 75,502 130,000
     
Construction Engineering 63,077 148,600
Construction Contract 1,824,491 2,180,734
Other Construction 0 95,060
Total Construction 1,887,568 2,424,394
     
Funding Surplus - 307,650  
Total TIB Funding 1,655,420 2,554,394

Local Funding Partners

Funding Amount Percent
SPOKANE VALLEY 606,159 23.7%
WSDOT Funding 0 0.0%
Spokane Co - CDBG  292,815 11.5%
 
 
 
 
 
 
 
Total Local Funding 898,974 35.2%

Project Description

Reconstruct intersection with PCCP extending about 200 feet from intersection. Replace portions of curb and sidewalk. The north, east, and south legs will be restriped to a typical 3 lane section with dedicated left turn lanes and bike lanes (west leg is not a bike route). New signal with a protected-permitted left turn signal phasing.

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments