Transportation Improvement Board
Performance Management Dashboard

 Projects — TIB Project Information

TIB Project Information

Spokane County's Bigelow Gulch Road

8-3-032(072)-1

8-3-032(072)-1
Bigelow Gulch Road

Progress Rd to Wellesley Ave

FY 2021 Urban Arterial Program
Current Phase : Construction
Total TIB Funding : $2,065,000

County: Spokane   |   Legislative District: 4   |   Project Length: 0.91   |   TIB Engineer: Andrew Beagle   |   Last Payment Date: 02/06/2024

Project Information

Lead Agency SPOKANE COUNTY
Funding Year 2021
Program UAP
Current Phase Construction
Legislative District 4
Congressional District 5
Federal Route Number 4103
Project Length 0.91 mi.
ADT 10,478
Functional Class Principal
Type of Work Minor Widening
Project Contact Tim Schwab
Contact Email tschwab@spokanecounty.org
TIB Engineer Andrew Beagle
Last Payment Date 02/06/2024
Cultural Resource Assessment Section 106

Project Schedule

  Target Date Actual Date
Project Selection Date   11/22/2019
Delayed Project Date 07/01/2024  
DAHP Assessment Date   06/18/2019
Predesign Approval
Design Approval 02/01/2020 01/07/2020
Bid Auth. Approval 07/01/2021 07/23/2021
Construction Approval 12/31/2021 01/06/2022
Project Closeout 02/15/2024
Audit Date  
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 0 0
Right of Way 0 0
Total Design 0 0
     
Construction Engineering 140,570 527,612
Construction Contract 1,924,430 4,883,092
Other Construction 0 0
Total Construction 2,065,000 5,410,704
     
Total TIB Funding 2,065,000 5,410,704

Local Funding Partners

Funding Amount Percent
SPOKANE COUNTY 0 0.0%
WSDOT Funding 0 0.0%
Federal (STBG(U))  963,360 17.8%
Federal (HIP(U))  573,575 10.6%
FMSIB  1,808,769 33.4%
 
 
 
 
 
Total Local Funding 3,345,704 61.8%

Project Description

A new roadway will be constructed on a new corridor alignment, connecting Forker Road directly to Sullivan Road at the Sullivan/Wellesley intersection, between East Valley Middle School and East Valley High School. The new alignment will eliminate the use of Progress Road from the Bigelow/Forker alignment. Generally, the urban roadway will consist of four lanes and a center turn lane. From Wellesley Avenue to Sullivan Road (about 1,100 feet), either a separated sidewalk or separated pathway will be constructed on both sides along with curb and gutter. The roadway section from Sullivan Road to Progress Road (about 2,500 feet) will also consist of 4 lanes and a center turn lane, with shoulders and a separated pathway on the west side of the road. A portion of the existing Forker/Progress intersection will be realigned to facilitate the change of direction for traffic. This project will tie into the City of Spokane Valley's Wellesley Avenue/Sullivan Road intersection project, toward which this project funding will contribute.

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments