Transportation Improvement Board
Performance Management Dashboard

 Projects — TIB Project Information

TIB Project Information

City of Mount Vernon's Hoag Road and Laventure Road

8-2-155(018)-1

8-2-155(018)-1
Hoag Road and Laventure Road

Laventure Rd Intersection

FY 2022 Urban Arterial Program
Current Phase : Audit
Total TIB Funding : $943,825

County: Skagit   |   Legislative District: 40   |   Project Length: 0.10   |   TIB Engineer: Chris Langhoff   |   Last Payment Date: 10/16/2023

Project Information

Lead Agency MOUNT VERNON
Funding Year 2022
Program UAP
Current Phase Audit
Legislative District 40
Congressional District 1
Federal Route Number 7295
Project Length 0.10 mi.
ADT 17,200
Functional Class Minor
Type of Work Safety
Project Contact William Bullock
Contact Email billb@mountvernonwa.gov
TIB Engineer Chris Langhoff
Last Payment Date 10/16/2023
Cultural Resource Assessment CRA

Project Schedule

  Target Date Actual Date
Project Selection Date   11/20/2020
Delayed Project Date 07/01/2025  
DAHP Assessment Date  
Predesign Approval
Design Approval 02/01/2021 02/08/2021
Bid Auth. Approval 01/31/2023 01/24/2023
Construction Approval 02/28/2023 02/28/2023
Project Closeout 10/31/2023 10/10/2023
Audit Date   10/16/2023
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 191,687 220,242
Right of Way 110,437 107,807
Total Design 302,124 328,049
     
Construction Engineering 95,449 135,258
Construction Contract 902,427 1,030,775
Other Construction 0 0
Total Construction 997,876 1,166,033
     
Funding Surplus - 356,175  
Total TIB Funding 943,825 1,494,082

Local Funding Partners

Funding Amount Percent
MOUNT VERNON 550,257 36.8%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 550,257 36.8%

Project Description

Planned improvements to this intersection include - Installation of an eight-phase signal system. - Two-inch grind and overlay to restore pavement defects and re-establish crown. - Sidewalk improvements to include closing two gaps in the alignment. - ADA ramp reconfiguration (shorten pedestrian crossing distance). - Positively established bike lanes. - Full intersection lighting. - A new transit pull-out on west-bound Hoag Road. - Underground aerial utilities required for signal clearance (not eligible). These improvements will remove a key bottleneck greatly decreasing the congestion in this corridor and increasing accessibility to jobs and commercial destinations in north Mount Vernon and the surrounding area. Pedestrians and bicyclist will have vastly improved access between the College and the YMCA which has become a substantial non-motorized generator for this locality.

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments