City of Covington's Lakepointe Boulevard
8-1-204(005)-2
8-1-204(005)-2
Lakepointe Boulevard
SR 18 to SE 258th St
FY 2021 Urban Arterial Program
Current Phase : Withdrawn
Total TIB Funding : $0
County: King | Legislative District: 47 | Project Length: 0.95 | TIB Engineer: Greg Armstrong | Last Payment Date:
Project Information
Lead Agency | COVINGTON |
Funding Year | 2021 |
Program | UAP |
Current Phase | Withdrawn |
Legislative District | 47 |
Congressional District | 8 |
Federal Route Number | 1170 |
Project Length | 0.95 mi. |
ADT | 0 |
Functional Class | Minor |
Type of Work | New Location |
Project Contact | Bob Lindskov |
Contact Email | blindskov@covingtonwa.gov |
TIB Engineer | Greg Armstrong |
Last Payment Date | |
Cultural Resource Assessment | Section 106 |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/22/2019 | |
Delayed Project Date | 07/01/2024 | |
DAHP Assessment Date | ||
Predesign Approval | ||
Design Approval | 02/01/2022 | 01/23/2022 |
Bid Auth. Approval | 01/15/2024 | |
Construction Approval | 02/29/2024 | |
Project Closeout | 06/30/2025 | |
Audit Date | ||
Withdrawn Date | 12/30/2023 |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 0 | 0 |
Right of Way | 0 | 0 |
Total Design | 0 | 0 |
Construction Engineering | 0 | 340,555 |
Construction Contract | 0 | 18,390,613 |
Other Construction | 0 | 0 |
Total Construction | 0 | 18,731,168 |
Total TIB Funding | 0 | 18,731,168 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
COVINGTON | 0 | 0.0% |
WSDOT Funding | 0 | 0.0% |
Lakepointe | 18,731,168 | 100.0% |
Total Local Funding | 18,731,168 | 100.0% |
Project Description
To provide the needed vehicle, active and transit mode connections to the new Lakepointe Urban Village development site, Lakepointe Boulevard is proposed as a 4-lane curb and gutter roadway with shared use paths, separated and on-road bike lanes and wide sidewalks separated from vehicle lanes by planter strips and/or stormwater treatment bioswales. The roadway improvements include roundabouts at three major intersections. Lakepointe Boulevard is one of three roadway projects being constructed concurrently by the City of Covington, completing the connection between SR 18 and SR 516. Other projects include two roundabouts at SR 18 and SE 256th Street connecting to Lakepointe Boulevard and new active mode facilities connected to SR 516. New and upgraded utilities for the new development will be constructed concurrent with the road improvements. The project will be constructed entirely within improved right of way dedicated to the City by the private developer, a process which is underway and will be completed by advertisement. An EIS for the site, including the road has been completed and approved. The project design plans will be 100% construction ready by November, 2019. The City has approved the plans for advertisement and no further permits are required.
Existing Condition
Project Benefits
Project Pictures
No images available.
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |