TIB Project Information

City of SeaTac's 34th Avenue S

8-1-121(009)-1

8-1-121(009)-1
34th Avenue S

S 160th St to S 166th St

FY 2022 Urban Arterial Program
Current Phase : Construction
Total TIB Funding : $2,000,000

County: King   |   Legislative District: 33   |   Project Length: 0.35   |   TIB Engineer: Greg Armstrong   |   Last Payment Date: 03/08/2024

Project Information

Lead Agency SEATAC
Funding Year 2022
Program UAP
Current Phase Construction
Legislative District 33
Congressional District 9
Federal Route Number 1295
Project Length 0.35 mi.
ADT 25,880
Functional Class Collector
Type of Work Reconstruction
Project Contact Pete Kang
Contact Email pkang@seatacwa.gov
TIB Engineer Greg Armstrong
Last Payment Date 03/08/2024
Cultural Resource Assessment Section 106

Project Schedule

  Target Date Actual Date
Project Selection Date   11/20/2020
Delayed Project Date 01/01/2022  
DAHP Assessment Date   04/19/2021
Predesign Approval
Design Approval 02/01/2021 01/28/2021
Bid Auth. Approval 04/23/2021 04/20/2021
Construction Approval 09/08/2021 09/08/2021
Project Closeout 05/31/2024
Audit Date  
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 0 0
Right of Way 0 0
Total Design 0 0
     
Construction Engineering 307,655 766,703
Construction Contract 1,692,345 6,046,133
Other Construction 0 0
Total Construction 2,000,000 6,812,836
     
Total TIB Funding 2,000,000 6,812,836

Local Funding Partners

Funding Amount Percent
SEATAC 2,348,836 34.5%
WSDOT Funding 0 0.0%
Safe Routes to School  2,464,000 37.8%
 
 
 
 
 
 
 
Total Local Funding 4,812,836 72.3%

Project Description

The project provides a safer, ADA-compliant walking area for neighborhood children and wheelchair users, who will be completely separated from bicycle and vehicular traffic through the construction of curb, gutter, sidewalks, and bicycle lanes on both sides of the road along the entire length of the project. Planter strips will be constructed to provide an additional buffer between pedestrians and vehicles. Pedestrian lighting will improve visibility. A flashing all-way stop at South 162nd and a Rectangular Rapid Flashing Beacon at South 160th Street will provide safer crossings for pedestrians. On-street parking will be constructed along the west side between South 162nd Street and South 166th Street. Curb extensions at intersections will help mitigate speeds, driveways bulb-outs will prevent on-street parking from blocking driveways and also help mitigate speeds. Pavement will consist of full-depth reclamation north of 162nd, and grind/overlay south of 162nd. The vertical profile will be smoothed out north of 162nd to eliminate a steep vertical curve, which will improve stopping sight distance. Obstructions at 160th will be removed improving intersection sight distance. The elimination of roadside ditches and utility poles will improve safety for all modes of travel along this roadway.

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments