Transportation Improvement Board
Performance Management Dashboard

 Projects — TIB Project Information

TIB Project Information

City of Raymond's 2021 Rehabilitation and Overlay

6-W-971(011)-1

6-W-971(011)-1
2021 Rehabilitation and Overlay

Fowler St to Ocean Ave

FY 2023 Small City Arterial Program
Current Phase : Audit
Total TIB Funding : $1,027,620

County: Pacific   |   Legislative District: 19   |   Project Length: 0.18   |   TIB Engineer: Chris Langhoff   |   Last Payment Date: 06/01/2023

Project Information

Lead Agency RAYMOND
Funding Year 2023
Program SCAP
Current Phase Audit
Legislative District 19
Congressional District 3
Federal Route Number 9999
Project Length 0.18 mi.
ADT 3,000
Functional Class TIB Arterial
Type of Work Reconstruction
Project Contact Eric Weiberg Director of Public Works
Contact Email ericweiberg@cityofraymond.com
TIB Engineer Chris Langhoff
Last Payment Date 06/01/2023
Cultural Resource Assessment CRA

Project Schedule

  Target Date Actual Date
Project Selection Date   11/19/2021
Delayed Project Date 07/01/2024  
DAHP Assessment Date  
Predesign Approval
Design Approval 01/15/2022 12/08/2021
Bid Auth. Approval 04/30/2022 05/27/2022
Construction Approval 07/15/2022 07/12/2022
Project Closeout 04/28/2023 05/24/2023
Audit Date   06/01/2023
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 109,250 114,733
Right of Way 0 0
Total Design 109,250 114,733
     
Construction Engineering 133,950 150,945
Construction Contract 929,412 823,471
Other Construction 0 0
Total Construction 1,063,362 974,416
     
Funding Surplus - 144,992  
Total TIB Funding 1,027,620 1,089,149

Local Funding Partners

Funding Amount Percent
RAYMOND 61,529 5.6%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 61,529 5.6%

Project Description

Willapa Place Way suffers from ponding water and flooding that regularly occurs during heavy rains. The project proposes to slightly raise the roadway profile, correct the roadway geometry and to add curbs, gutters, catch basins and conveyance. The proposed solution for Franklin Street is to rebuild the 550 foot section using the FDR process. Barnhart street will be paved with with 2 inches of HMA with limited pavement repair/prelevel.

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments