Rush Road connects the community of Napavine to Interstate 5. Due to heavy traffic counts and loads, Rush Road has experienced multiple forms of failure over its length. Failure includes fatigue cracks, alligator cracking, and rutting.
Projects — TIB Project Information
TIB Project Information
City of Napavine's 2023 Rush Road Repairs
6-W-963(009)-1
6-W-963(009)-1
2023 Rush Road Repairs
Varies
FY 2024 Small City Arterial Program
Current Phase : Audit
Total TIB Funding : $302,339
County: Lewis | Legislative District: 20 | Project Length: 0.19 | TIB Engineer: Chris Langhoff | Last Payment Date: 01/31/2024
Project Information
Lead Agency | NAPAVINE |
Funding Year | 2024 |
Program | SCAP |
Current Phase | Audit |
Legislative District | 20 |
Congressional District | 3 |
Federal Route Number | 5657 |
Project Length | 0.19 mi. |
ADT | 1,500 |
Functional Class | Minor |
Type of Work | Reconstruction |
Project Contact | David Nielsen |
Contact Email | admin@jacksoncivil.com |
TIB Engineer | Chris Langhoff |
Last Payment Date | 01/31/2024 |
Cultural Resource Assessment | Not Required |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 12/02/2022 | |
Delayed Project Date | 07/01/2025 | |
DAHP Assessment Date | ||
Predesign Approval | ||
Design Approval | 02/28/2023 | 03/17/2023 |
Bid Auth. Approval | 04/15/2023 | 05/01/2023 |
Construction Approval | 05/31/2023 | 07/12/2023 |
Project Closeout | 01/31/2024 | 01/16/2024 |
Audit Date | 01/31/2024 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 42,750 | 45,000 |
Right of Way | 0 | 0 |
Total Design | 42,750 | 45,000 |
Construction Engineering | 17,670 | 27,234 |
Construction Contract | 202,154 | 246,018 |
Other Construction | 0 | 0 |
Total Construction | 219,824 | 273,252 |
Funding Increase | 39,765 | |
Total TIB Funding | 302,339 | 318,252 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
NAPAVINE | 15,913 | 5.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 15,913 | 5.0% |
Project Description
The project proposes to reconstruction sections of Rush Road via grind and inlay. Due to heavy traffic loads, a 8-inch asphalt section is proposed.
Existing Condition
Project Benefits
- Improves arterial network;
- Restores structural condition
Project Pictures
No images available.
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |