The area and need for access improvements was first identified in the Yakima County Development Associations SR 24 Industrial Sub-Area Plan, published in 2004. SR 24 is both the main entrance and exit route to the City of Moxee from the west. Existing North-South Arterials, Beaudry Road and Birchfield Road, intersect SR 24, are spaced approximately 1.7 miles apart, and include heavy vehicle traffic due to industrial land use. Large parcels of undeveloped, industrial and commercial zoned land are bounded by Birchfield Road, Beaudry Road, Mieras Road, and State Route 24, but direct access is a missing component to this relatively flat land with railroad access and close proximity to Interstate 82. YVCOG awarded Moxee $1,491,430 in STP funding and requires a 13.5% match. The City is requesting TIB funding to cover 95% of the required match or $271,045 in funding to complete the project.
Projects — TIB Project Information
TIB Project Information
City of Moxee's Morrier Lane Extension
6-E-943(006)-1
6-E-943(006)-1
Morrier Lane Extension
Duffield Rd Roundabout to Mieras Rd
FY 2022 Small City Arterial Program
Current Phase : Audit
Total TIB Funding : $252,640
County: Yakima | Legislative District: 15 | Project Length: 0.40 | TIB Engineer: Jonathan Heusman | Last Payment Date: 06/01/2023
Project Information
Lead Agency | MOXEE |
Funding Year | 2022 |
Program | SCAP |
Current Phase | Audit |
Legislative District | 15 |
Congressional District | 4 |
Federal Route Number | 4669 |
Project Length | 0.40 mi. |
ADT | 0 |
Functional Class | Minor |
Type of Work | New Location |
Project Contact | Byron Adams |
Contact Email | byron.adams@co.yakima.wa.us |
TIB Engineer | Jonathan Heusman |
Last Payment Date | 06/01/2023 |
Cultural Resource Assessment | Section 106 |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/20/2020 | |
Delayed Project Date | 07/01/2023 | |
DAHP Assessment Date | 09/13/2019 | |
Predesign Approval | ||
Design Approval | 02/01/2021 | 12/27/2020 |
Bid Auth. Approval | 08/01/2021 | 07/15/2021 |
Construction Approval | 09/10/2021 | 09/08/2021 |
Project Closeout | 05/31/2023 | 05/17/2023 |
Audit Date | 06/01/2023 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 25,925 | 233,055 |
Right of Way | 0 | 0 |
Total Design | 25,925 | 233,055 |
Construction Engineering | 28,085 | 230,520 |
Construction Contract | 216,044 | 1,456,930 |
Other Construction | 992 | 2,542 |
Total Construction | 245,121 | 1,689,992 |
Funding Surplus | - 18,406 | |
Total TIB Funding | 252,640 | 1,923,047 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
MOXEE | 6,973 | 0.4% |
WSDOT Funding | 0 | 0.0% |
Federal Funding | 1,663,435 | 86.5% |
Total Local Funding | 1,670,407 | 86.9% |
Project Description
The project will extend approximately 2,600 LF of 45-foot wide arterial known as Morrier Lane from Duffield Road to Mieras Road. Proposed construction will connect Mieras Road to the previous, STP funded, Morrier Lane/ SR 24 Intersection Improvement project. The project included a three-lane urban section with bike lanes, curb and gutter, 6 sidewalk on both sides, handicap ramps at intersections, storm drainage facilities, and illumination system. Extending Morrier Lane north to Mieras will provide additional connectivity to the existing roadway network within Moxee. The extension will provide direct vehicular access from Mieras Road to SR 24, reducing the demand on Birchfield Road and Beaudry Road.
Existing Condition
Project Benefits
- Improves arterial network;
- Extends improvements
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |