TIB Project Information

Town of Granger's Main Street Phase 1

6-E-940(005)-1

6-E-940(005)-1
Main Street Phase 1

1st St to 2nd St

FY 2023 Small City Arterial Program
Current Phase : Construction
Total TIB Funding : $1,061,439

County: Yakima   |   Legislative District: 15   |   Project Length: 0.10   |   TIB Engineer: Jonathan Heusman   |   Last Payment Date: 11/17/2023

Project Information

Lead Agency GRANGER
Funding Year 2023
Program SCAP
Current Phase Construction
Legislative District 15
Congressional District 4
Federal Route Number 9999
Project Length 0.10 mi.
ADT 1,179
Functional Class TIB Arterial
Type of Work Reconstruction
Project Contact Jodie Luke
Contact Email jluke.granger@co.yakima.wa.us
TIB Engineer Jonathan Heusman
Last Payment Date 11/17/2023
Cultural Resource Assessment CRA

Project Schedule

  Target Date Actual Date
Project Selection Date   11/19/2021
Delayed Project Date 07/01/2024  
DAHP Assessment Date   04/13/2023
Predesign Approval
Design Approval 02/01/2022 12/16/2021
Bid Auth. Approval 04/15/2023 04/13/2023
Construction Approval 05/31/2023 05/10/2023
Project Closeout 03/31/2024
Audit Date  
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 108,044 113,730
Right of Way 0 0
Total Design 108,044 113,730
     
Construction Engineering 108,044 113,730
Construction Contract 720,351 1,040,684
Other Construction 0 0
Total Construction 828,395 1,154,414
     
Funding Increase 125,000  
Total TIB Funding 1,061,439 1,268,144

Local Funding Partners

Funding Amount Percent
GRANGER 206,705 16.3%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 206,705 16.3%

Project Description

The project will make improvements which enhance business access, increase economic activity, and improve safety to pedestrians in the City. Reconstruction of Main Street will include constructing a new asphalt roadway and subbase, new sidewalks and bulb-outs, and ADA-compliant curb ramps. A new concrete median, which could serve as a refuge for pedestrians, will be constructed along with drainage and infiltration improvements, and new pavement markings.

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments