East 1st Avenue connects Main Street in the City of Kittitas to Park Creek Rd, which is a collector street for Kittitas County. The road is classified as a T-3 truck route with a PCR ranging from 21 to 32, indicating a need for reconstruction. The poor condition of the roadway causes trucks to use an alternative truck route to enter the City on Clerf Road, Patrick Avenue, and Main Street. The use of this alternative route places additional stress on these roads. Completion of this project will restore the truck route connecting the City of Kittitas to Kittitas County and help to protect the City's other major streets.
Projects — TIB Project Information
TIB Project Information
City of Kittitas's E 1st Avenue
6-E-931(I05)-1
6-E-931(I05)-1
E 1st Avenue
Main St to East C/L
FY 2020 Small City Arterial Program
Current Phase : Construction
Total TIB Funding : $87,751
County: Kittitas | Legislative District: 13 | Project Length: 0.32 | TIB Engineer: Jonathan Heusman | Last Payment Date: 02/08/2023
Project Information
Lead Agency | KITTITAS |
Funding Year | 2020 |
Program | SCAP |
Current Phase | Construction |
Legislative District | 13 |
Congressional District | 8 |
Federal Route Number | 19CQ |
Project Length | 0.32 mi. |
ADT | 1,000 |
Functional Class | Collector |
Type of Work | Reconstruction |
Project Contact | Debbie Lee |
Contact Email | debbie.lee@cityofkittitas.com |
TIB Engineer | Jonathan Heusman |
Last Payment Date | 02/08/2023 |
Cultural Resource Assessment | Section 106 |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/16/2018 | |
Delayed Project Date | 07/01/2021 | |
DAHP Assessment Date | 10/27/2020 | |
Predesign Approval | ||
Design Approval | 01/01/2019 | 01/15/2019 |
Bid Auth. Approval | 09/15/2021 | 09/17/2021 |
Construction Approval | 12/17/2021 | 01/28/2022 |
Project Closeout | 05/31/2024 | |
Audit Date | ||
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 9,383 | 69,501 |
Right of Way | 0 | 0 |
Total Design | 9,383 | 69,501 |
Construction Engineering | 8,708 | 64,501 |
Construction Contract | 69,660 | 516,000 |
Other Construction | 0 | 0 |
Total Construction | 78,368 | 580,501 |
Total TIB Funding | 87,751 | 650,002 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
KITTITAS | 0 | 0.0% |
WSDOT Funding | 0 | 0.0% |
STBG Regional Federal Funds | 562,251 | 86.5% |
Total Local Funding | 562,251 | 86.5% |
Project Description
The roadway will be pulverized and strengthened with cement treated base. The roadway section will be strengthened according to the recommendations of a geotechnical report to support the truck traffic through this area. The roadway geometry will be designed to accommodate the truck traffic and minor changes may be made to the intersection geometry of East 1st Avenue and Clark Street.
Existing Condition
Project Benefits
- Improves safety;
- Restores structural condition
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |