City of Cle Elum's First Street

6-E-930(006)-1

6-E-930(006)-1
First Street

Pennsylvania Ave to Harris Ave

FY 2024 Small City Arterial Program
Current Phase : Construction
Total TIB Funding : $718,849

County: Kittitas   |   Legislative District: 13   |   Project Length: 0.80   |   TIB Engineer: Jonathan Heusman   |   Last Payment Date: 03/13/2024

Project Information

Lead Agency CLE ELUM
Funding Year 2024
Program SCAP
Current Phase Construction
Legislative District 13
Congressional District 8
Federal Route Number 0903
Project Length 0.80 mi.
ADT 7,521
Functional Class Collector
Type of Work Reconstruction
Project Contact Rob Omans
Contact Email romans@cleelum.gov
TIB Engineer Jonathan Heusman
Last Payment Date 03/13/2024
Cultural Resource Assessment Not Required

Project Schedule

  Target Date Actual Date
Project Selection Date   12/02/2022
Delayed Project Date 07/01/2025  
DAHP Assessment Date  
Predesign Approval
Design Approval 02/01/2023 01/23/2023
Bid Auth. Approval 04/15/2023 02/24/2023
Construction Approval 05/06/2023 04/04/2023
Project Closeout 02/28/2024
Audit Date  
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 14,250 15,000
Right of Way 0 0
Total Design 14,250 15,000
     
Construction Engineering 90,060 183,450
Construction Contract 495,790 713,396
Other Construction 118,749 185,000
Total Construction 704,599 1,081,846
     
Total TIB Funding 718,849 1,096,846

Local Funding Partners

Funding Amount Percent
CLE ELUM 377,997 34.5%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 377,997 34.5%

Project Description

A road diet to narrow the roadway to 11-foot travel lane widths to promote speed calming, increase parking in a safer orientation, and add wide sidewalk and pedestrian amenities to slow traffic in the downtown area.

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments