6th Street is one of the busiest roads in Coulee Dam serving the Casino, church, US Post Office, and grocery store. The roadway was originally construction out of concrete during the construction of Coulee Dam in the 1940s. The concrete cold joints have deteriorated through the decades resulting in full-depth voids up to 5 inches in width and is the Citys number one project. Various efforts have been made through the years to bridge reflected cracks, including various fabric, and overlays to no avail. The existing roadway has discontinuous sidewalks on one side, and existing crosswalks going across 6th Street do not have ramps.
Projects — TIB Project Information
TIB Project Information
Town of Coulee Dam's 6th Street
6-E-878(007)-1
6-E-878(007)-1
6th Street
Aspen St to Central Drive
FY 2023 Small City Arterial Program
Current Phase : Audit
Total TIB Funding : $829,851
County: Okanogan/Douglas/Grant | Legislative District: 12 | Project Length: 0.25 | TIB Engineer: Andrew Beagle | Last Payment Date: 11/15/2023
Project Information
Lead Agency | COULEE DAM |
Funding Year | 2023 |
Program | SCAP |
Current Phase | Audit |
Legislative District | 12 |
Congressional District | 4 |
Federal Route Number | 9999 |
Project Length | 0.25 mi. |
ADT | 500 |
Functional Class | TIB Arterial |
Type of Work | Resurfacing |
Project Contact | Stefani Bowden |
Contact Email | cdclerk@couleedam.org |
TIB Engineer | Andrew Beagle |
Last Payment Date | 11/15/2023 |
Cultural Resource Assessment | Not Required |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/19/2021 | |
Delayed Project Date | 07/01/2024 | |
DAHP Assessment Date | ||
Predesign Approval | ||
Design Approval | 02/15/2022 | 02/14/2022 |
Bid Auth. Approval | 11/01/2022 | 10/27/2022 |
Construction Approval | 12/01/2022 | 01/26/2023 |
Project Closeout | 12/31/2023 | 11/09/2023 |
Audit Date | 11/15/2023 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 86,946 | 63,000 |
Right of Way | 0 | 0 |
Total Design | 86,946 | 63,000 |
Construction Engineering | 86,945 | 119,100 |
Construction Contract | 579,637 | 615,853 |
Other Construction | 28,982 | 31,898 |
Total Construction | 695,564 | 766,851 |
Funding Increase | 47,341 | |
Total TIB Funding | 829,851 | 829,851 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
COULEE DAM | 0 | 0.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 0 | 0.0% |
Project Description
Reconstruction of the roadway will include grinding off the existing asphalt overlays, and rubblizing the existing concrete in place. The rubblizing concrete will make up the roadway base which will be graded to subgrade with some CSTC and surfaced with HMA. 23 ADA ramp upgrades at the pedestrian crossings.
Existing Condition
Project Benefits
- Restores structural condition;
- Removes ADA barriers
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |