Transportation Improvement Board
Performance Management Dashboard

 Projects — TIB Project Information

TIB Project Information

Town of Coulee Dam's 6th Street

6-E-878(007)-1

6-E-878(007)-1
6th Street

Aspen St to Central Drive

FY 2023 Small City Arterial Program
Current Phase : Audit
Total TIB Funding : $829,851

County: Okanogan/Douglas/Grant   |   Legislative District: 12   |   Project Length: 0.25   |   TIB Engineer: Andrew Beagle   |   Last Payment Date: 11/15/2023

Project Information

Lead Agency COULEE DAM
Funding Year 2023
Program SCAP
Current Phase Audit
Legislative District 12
Congressional District 4
Federal Route Number 9999
Project Length 0.25 mi.
ADT 500
Functional Class TIB Arterial
Type of Work Resurfacing
Project Contact Stefani Bowden
Contact Email cdclerk@couleedam.org
TIB Engineer Andrew Beagle
Last Payment Date 11/15/2023
Cultural Resource Assessment Not Required

Project Schedule

  Target Date Actual Date
Project Selection Date   11/19/2021
Delayed Project Date 07/01/2024  
DAHP Assessment Date  
Predesign Approval
Design Approval 02/15/2022 02/14/2022
Bid Auth. Approval 11/01/2022 10/27/2022
Construction Approval 12/01/2022 01/26/2023
Project Closeout 12/31/2023 11/09/2023
Audit Date   11/15/2023
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 86,946 63,000
Right of Way 0 0
Total Design 86,946 63,000
     
Construction Engineering 86,945 119,100
Construction Contract 579,637 615,853
Other Construction 28,982 31,898
Total Construction 695,564 766,851
     
Funding Increase 47,341  
Total TIB Funding 829,851 829,851

Local Funding Partners

Funding Amount Percent
COULEE DAM 0 0.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 0 0.0%

Project Description

Reconstruction of the roadway will include grinding off the existing asphalt overlays, and rubblizing the existing concrete in place. The rubblizing concrete will make up the roadway base which will be graded to subgrade with some CSTC and surfaced with HMA. 23 ADA ramp upgrades at the pedestrian crossings.

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments