8th Street and Selkirk Avenue (south of 4th Street) serve the densely populated southern portion of the City, including the Chausee Mobile Home Court and Cox Addition neighborhoods, as well as Our Lady of the Desert Church. These streets both have a PCR score under 21, indicating a need for reconstruction. Because of the poor condition of these streets, it is difficult for residents to use the corridor along 8th Street and Selkirk Avenue. As the City continues to grow to the south, the central location of Selkirk and the location of 8th makes these streets the most likely to serve as arterials.
Projects — TIB Project Information
TIB Project Information
Town of Mattawa's 8th Street / Selkirk Avenue
6-E-862(002)-1
6-E-862(002)-1
8th Street / Selkirk Avenue
Portage Ave to 4th St
FY 2023 Small City Arterial Program
Current Phase : Audit
Total TIB Funding : $482,820
County: Grant | Legislative District: 13 | Project Length: 0.55 | TIB Engineer: Jonathan Heusman | Last Payment Date: 01/17/2023
Project Information
Lead Agency | MATTAWA |
Funding Year | 2023 |
Program | SCAP |
Current Phase | Audit |
Legislative District | 13 |
Congressional District | 4 |
Federal Route Number | 9999 |
Project Length | 0.55 mi. |
ADT | 750 |
Functional Class | TIB Arterial |
Type of Work | Reconstruction |
Project Contact | Juan Ledezma |
Contact Email | jledezma@cityofmattawa-wa.gov |
TIB Engineer | Jonathan Heusman |
Last Payment Date | 01/17/2023 |
Cultural Resource Assessment | Not Required |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/19/2021 | |
Delayed Project Date | 07/01/2024 | |
DAHP Assessment Date | ||
Predesign Approval | ||
Design Approval | 01/01/2022 | 12/16/2021 |
Bid Auth. Approval | 05/30/2022 | 05/27/2022 |
Construction Approval | 06/25/2022 | 07/13/2022 |
Project Closeout | 12/30/2022 | 01/04/2023 |
Audit Date | 01/17/2023 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 57,060 | 63,400 |
Right of Way | 0 | 0 |
Total Design | 57,060 | 63,400 |
Construction Engineering | 57,060 | 62,994 |
Construction Contract | 380,727 | 410,073 |
Other Construction | 0 | 0 |
Total Construction | 437,787 | 473,067 |
Funding Surplus | - 12,027 | |
Total TIB Funding | 482,820 | 536,467 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
MATTAWA | 53,647 | 10.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 53,647 | 10.0% |
Project Description
The proposed roadway improvements will pulverize the existing roadway to construct a suitable roadway base, prelevel the roadway with crushed surfacing material, and repave the roadway. 11-foot travel lanes will be established. The proposed roadway improvements will eliminate the gap of roadways in acceptable conditions for residents using the corridor along 8th Street and Selkirk Avenue, from the south end of Portage Ave to 4th St.
Existing Condition
Project Benefits
- Improves safety;
- Completes gap;
- Restores structural condition
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |