TIB Project Information

City of Grand Coulee's James Saunder Street and Fortuyn Road

6-E-859(003)-1

6-E-859(003)-1
James Saunder Street and Fortuyn Road

Burdin Blvd to 2nd St

FY 2024 Small City Arterial Program
Current Phase : Construction
Total TIB Funding : $824,918

County: Grant   |   Legislative District: 12   |   Project Length: 0.18   |   TIB Engineer: Andrew Beagle   |   Last Payment Date: 02/21/2024

Project Information

Lead Agency GRAND COULEE
Funding Year 2024
Program SCAP
Current Phase Construction
Legislative District 12
Congressional District 4
Federal Route Number 9999
Project Length 0.18 mi.
ADT 375
Functional Class TIB Arterial
Type of Work Reconstruction
Project Contact Lorna Pearce
Contact Email clerkgc@gccitywa.org
TIB Engineer Andrew Beagle
Last Payment Date 02/21/2024
Cultural Resource Assessment Not Required

Project Schedule

  Target Date Actual Date
Project Selection Date   12/02/2022
Delayed Project Date 07/01/2025  
DAHP Assessment Date  
Predesign Approval
Design Approval 02/01/2023 12/14/2022
Bid Auth. Approval 02/15/2024 02/22/2024
Construction Approval 03/15/2024 03/26/2024
Project Closeout 10/01/2024
Audit Date  
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 92,300 92,300
Right of Way 0 0
Total Design 92,300 92,300
     
Construction Engineering 92,300 92,300
Construction Contract 615,400 640,318
Other Construction 0 0
Total Construction 707,700 732,618
     
Funding Increase 24,918  
Total TIB Funding 824,918 824,918

Local Funding Partners

Funding Amount Percent
GRAND COULEE 0 0.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 0 0.0%

Project Description

The project will pulverize, regrade, and add cement to the base, repave the roadway, add curb, gutter, and storm drainage, and sidewalk. This will provide restore the road condition, mitigate concerns from ambulance drivers and others accessing the medical center, collect stormwater to prevent further deterioration of the roadway, and improve pedestrian access. Additional countermeasures to wrong-way driving such as striping and signage will be added.

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments