James Saunders Street and Fortuyn Road provide access to the Coulee Medical Center, including an emergency department and other medical services. The road lacks storm drainage and also has deteriorated and ambulance drivers have expressed concern about the poor condition and bumpiness while driving to the medical center. Fortuyn is a one way road with minimal countermeasures to wrong-way driving. Pedestrian facilities along the route are intermittent.
Projects — TIB Project Information
TIB Project Information
City of Grand Coulee's James Saunder Street and Fortuyn Road
6-E-859(003)-1
6-E-859(003)-1
James Saunder Street and Fortuyn Road
Burdin Blvd to 2nd St
FY 2024 Small City Arterial Program
Current Phase : Construction
Total TIB Funding : $824,918
County: Grant | Legislative District: 12 | Project Length: 0.18 | TIB Engineer: Andrew Beagle | Last Payment Date: 02/21/2024
Project Information
Lead Agency | GRAND COULEE |
Funding Year | 2024 |
Program | SCAP |
Current Phase | Construction |
Legislative District | 12 |
Congressional District | 4 |
Federal Route Number | 9999 |
Project Length | 0.18 mi. |
ADT | 375 |
Functional Class | TIB Arterial |
Type of Work | Reconstruction |
Project Contact | Lorna Pearce |
Contact Email | clerkgc@gccitywa.org |
TIB Engineer | Andrew Beagle |
Last Payment Date | 02/21/2024 |
Cultural Resource Assessment | Not Required |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 12/02/2022 | |
Delayed Project Date | 07/01/2025 | |
DAHP Assessment Date | ||
Predesign Approval | ||
Design Approval | 02/01/2023 | 12/14/2022 |
Bid Auth. Approval | 02/15/2024 | 02/22/2024 |
Construction Approval | 03/15/2024 | 03/26/2024 |
Project Closeout | 10/01/2024 | |
Audit Date | ||
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 92,300 | 92,300 |
Right of Way | 0 | 0 |
Total Design | 92,300 | 92,300 |
Construction Engineering | 92,300 | 92,300 |
Construction Contract | 615,400 | 640,318 |
Other Construction | 0 | 0 |
Total Construction | 707,700 | 732,618 |
Funding Increase | 24,918 | |
Total TIB Funding | 824,918 | 824,918 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
GRAND COULEE | 0 | 0.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 0 | 0.0% |
Project Description
The project will pulverize, regrade, and add cement to the base, repave the roadway, add curb, gutter, and storm drainage, and sidewalk. This will provide restore the road condition, mitigate concerns from ambulance drivers and others accessing the medical center, collect stormwater to prevent further deterioration of the roadway, and improve pedestrian access. Additional countermeasures to wrong-way driving such as striping and signage will be added.
Existing Condition
Project Benefits
- Improves pedestrian safety;
- Improves vehicle and pedestrian access;
- Restores structural condition;
- Incorporates recycled materials
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |