The road was last assessed in 2020 and received a rating ranging from 59-72, indicating that the road is still capable of being overlaid without major subgrade repair. Walnut Street is a T-5 truck route. The roadway also connects to the Coulee City Food Center, Coulee City Medical Clinic, Banks Lake Lodge, the elementary and high school campus, and the rodeo grounds.
Projects — TIB Project Information
TIB Project Information
Town of Coulee City's Walnut Street Overlay
6-E-856(I04)-1
6-E-856(I04)-1
Walnut Street Overlay
4th St to Mc Entee St
FY 2024 Small City Arterial Program
Current Phase : Construction
Total TIB Funding : $58,736
County: Grant | Legislative District: 12 | Project Length: 0.27 | TIB Engineer: Andrew Beagle | Last Payment Date: 12/19/2023
Project Information
Lead Agency | COULEE CITY |
Funding Year | 2024 |
Program | SCAP |
Current Phase | Construction |
Legislative District | 12 |
Congressional District | 4 |
Federal Route Number | Q137 |
Project Length | 0.27 mi. |
ADT | 750 |
Functional Class | Collector |
Type of Work | Resurfacing |
Project Contact | Natalie Garrett |
Contact Email | tcoulee@odessaoffice.com |
TIB Engineer | Andrew Beagle |
Last Payment Date | 12/19/2023 |
Cultural Resource Assessment | Section 106 |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 12/02/2022 | |
Delayed Project Date | 07/01/2025 | |
DAHP Assessment Date | 05/19/2023 | |
Predesign Approval | ||
Design Approval | 02/01/2023 | 02/09/2023 |
Bid Auth. Approval | 08/02/2023 | 08/02/2023 |
Construction Approval | 08/20/2023 | 08/31/2023 |
Project Closeout | 02/28/2024 | |
Audit Date | ||
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 7,007 | 49,900 |
Right of Way | 0 | 0 |
Total Design | 7,007 | 49,900 |
Construction Engineering | 7,007 | 49,900 |
Construction Contract | 46,737 | 338,274 |
Other Construction | 0 | 0 |
Total Construction | 53,744 | 388,174 |
Funding Surplus | - 2,015 | |
Total TIB Funding | 58,736 | 438,074 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
COULEE CITY | 0 | 0.0% |
WSDOT Funding | 0 | 0.0% |
Grant County STBG | 379,338 | 86.6% |
Total Local Funding | 379,338 | 86.5% |
Project Description
HMA Overlay.
Existing Condition
Project Benefits
- Restores structural condition
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |