This section of Main Ave is provide primary access to the downtown business areas. This project was submitted and awarded by TIB last year in 2019 as SCPP project number Main Ave 2-E-845(007)-1. The project was to resurface this section of street with chip seal and slurry seal. The local downtown business rely on this street for access to there businesses and the appearance to the business
Projects — TIB Project Information
TIB Project Information
City of Ritzville's Main Avenue
6-E-845(008)-1
6-E-845(008)-1
Main Avenue
Palouse St to Jackson St
FY 2022 Small City Arterial Program
Current Phase : Audit
Total TIB Funding : $355,601
County: Adams | Legislative District: 9 | Project Length: 0.35 | TIB Engineer: Jonathan Heusman | Last Payment Date: 10/31/2023
Project Information
Lead Agency | RITZVILLE |
Funding Year | 2022 |
Program | SCAP |
Current Phase | Audit |
Legislative District | 9 |
Congressional District | 4 |
Federal Route Number | 9999 |
Project Length | 0.35 mi. |
ADT | 550 |
Functional Class | TIB Arterial |
Type of Work | Resurfacing |
Project Contact | Scott Yaeger |
Contact Email | scotty@co.adams.wa.us |
TIB Engineer | Jonathan Heusman |
Last Payment Date | 10/31/2023 |
Cultural Resource Assessment | Not Required |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/20/2020 | |
Delayed Project Date | 07/01/2023 | |
DAHP Assessment Date | ||
Predesign Approval | ||
Design Approval | 02/01/2021 | 12/18/2020 |
Bid Auth. Approval | 03/15/2021 | 03/18/2021 |
Construction Approval | 05/05/2021 | 05/05/2021 |
Project Closeout | 10/31/2023 | 10/19/2023 |
Audit Date | 10/31/2023 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 9,500 | 30,113 |
Right of Way | 0 | 0 |
Total Design | 9,500 | 30,113 |
Construction Engineering | 43,700 | 37,799 |
Construction Contract | 253,413 | 305,302 |
Other Construction | 23,988 | 16,467 |
Total Construction | 321,101 | 359,568 |
Funding Increase | 25,000 | |
Total TIB Funding | 355,601 | 389,681 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
RITZVILLE | 34,080 | 8.7% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 34,080 | 8.7% |
Project Description
This section of street was last slurry sealed in approximately 2004 and is in need of pavement preservation to seal the existing pavement. This project involves updating 22 ADA ramp to meet current standards, pavement repair and pre-level in areas showing distress, Adams County to provide and chip seal, and Contractor to provide a Slurry Seal over the chip seal for smoothness. The existing surfacing and subsurface have withstood the traffic loading and have proven to be sufficient still today. The City of Ritzville was able to secure TIB funding last year 2019 for this project Main Ave 2-E-845(007)-1 and the Cities Engineering firm has gotten to the point for establishing a estimate for the work planned but the funding was short by approximately $90,000. TIB staff and Director has suggested that the City withdrawl this project and submitt this project in 2020 under the SCAP Project application.
Existing Condition
Project Benefits
- Improves pedestrian safety;
- Supports economic development;
- Improves vehicle and pedestrian access;
- Removes ADA barriers
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |