The pavement condition rating of National Avenue - Chamber Way to Kresky Ave 48.
Projects — TIB Project Information
TIB Project Information
City of Chehalis's National Avenue Overlay
3-W-193(005)-1
3-W-193(005)-1
National Avenue Overlay
Chamber Way to Kresky Ave
FY 2023 Arterial Preservation Program
Current Phase : Audit
Total TIB Funding : $409,384
County: Lewis | Legislative District: 20 | Project Length: 0.36 | TIB Engineer: Chris Langhoff | Last Payment Date: 04/17/2023
Project Information
Lead Agency | CHEHALIS |
Funding Year | 2023 |
Program | APP |
Current Phase | Audit |
Legislative District | 20 |
Congressional District | 3 |
Federal Route Number | 5667 |
Project Length | 0.36 mi. |
ADT | 0 |
Functional Class | Principal |
Type of Work | Resurfacing |
Project Contact | Trent Lougheed |
Contact Email | tlougheed@ci.chehalis.wa.us |
TIB Engineer | Chris Langhoff |
Last Payment Date | 04/17/2023 |
Cultural Resource Assessment | Not Required |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/19/2021 | |
Delayed Project Date | 07/01/2024 | |
DAHP Assessment Date | ||
Predesign Approval | ||
Design Approval | 03/01/2022 | 03/10/2022 |
Bid Auth. Approval | 06/01/2022 | 06/14/2022 |
Construction Approval | 07/01/2022 | 07/05/2022 |
Project Closeout | 03/01/2023 | 04/10/2023 |
Audit Date | 04/17/2023 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 57,177 | 34,540 |
Right of Way | 0 | 0 |
Total Design | 57,177 | 34,540 |
Construction Engineering | 57,177 | 32,696 |
Construction Contract | 381,150 | 387,627 |
Other Construction | 0 | 0 |
Total Construction | 438,327 | 420,323 |
Funding Surplus | - 86,120 | |
Total TIB Funding | 409,384 | 454,863 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
CHEHALIS | 45,479 | 10.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 45,479 | 10.0% |
Project Description
Perform a 2-inch grind and overlay of the existing pavement, and roadway striping.
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |