The pavement condition rating of Main Street - I-5 to BNSF R/W is 48.
Projects — TIB Project Information
TIB Project Information
City of Chehalis's Main Street Overlay
3-W-193(004)-1
3-W-193(004)-1
Main Street Overlay
I 5 to BNSF R/W
FY 2023 Arterial Preservation Program
Current Phase : Audit
Total TIB Funding : $586,170
County: Lewis | Legislative District: 20 | Project Length: 0.27 | TIB Engineer: Chris Langhoff | Last Payment Date: 11/01/2023
Project Information
Lead Agency | CHEHALIS |
Funding Year | 2023 |
Program | APP |
Current Phase | Audit |
Legislative District | 20 |
Congressional District | 3 |
Federal Route Number | 5647 |
Project Length | 0.27 mi. |
ADT | 0 |
Functional Class | Principal |
Type of Work | Resurfacing |
Project Contact | Lance Bunker |
Contact Email | lbunker@ci.chehalis.wa.us |
TIB Engineer | Chris Langhoff |
Last Payment Date | 11/01/2023 |
Cultural Resource Assessment | Not Required |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/19/2021 | |
Delayed Project Date | 07/01/2024 | |
DAHP Assessment Date | ||
Predesign Approval | ||
Design Approval | 03/01/2022 | 03/10/2022 |
Bid Auth. Approval | 06/01/2023 | 04/10/2023 |
Construction Approval | 05/10/2023 | 05/01/2023 |
Project Closeout | 10/30/2023 | 10/30/2023 |
Audit Date | 11/01/2023 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 67,635 | 75,150 |
Right of Way | 0 | 0 |
Total Design | 67,635 | 75,150 |
Construction Engineering | 67,635 | 78,157 |
Construction Contract | 450,900 | 529,548 |
Other Construction | 0 | 0 |
Total Construction | 518,535 | 607,705 |
Total TIB Funding | 586,170 | 682,855 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
CHEHALIS | 96,685 | 14.2% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 96,685 | 14.2% |
Project Description
Perform a 2-inch grind and overlay of the existing pavement, roadway striping, and replacement of existing ADA ramps.
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |