TIB Project Information

City of Aberdeen's 2022 Overlay Award

3-W-189(008)-1

3-W-189(008)-1
2022 Overlay Award

Multiple Locations

FY 2024 Arterial Preservation Program
Current Phase : Audit
Total TIB Funding : $452,717

County: Grays Harbor   |   Legislative District: 19   |   Project Length: 0.40   |   TIB Engineer: Chris Langhoff   |   Last Payment Date: 12/14/2023

Project Information

Lead Agency ABERDEEN
Funding Year 2024
Program APP
Current Phase Audit
Legislative District 19
Congressional District 6
Federal Route Number 4981
Project Length 0.40 mi.
ADT 0
Functional Class Minor
Type of Work Resurfacing
Project Contact Edward D Mock
Contact Email emock@aberdeenwa.gov
TIB Engineer Chris Langhoff
Last Payment Date 12/14/2023
Cultural Resource Assessment Not Required

Project Schedule

  Target Date Actual Date
Project Selection Date   12/02/2022
Delayed Project Date 01/01/2024  
DAHP Assessment Date  
Predesign Approval
Design Approval 02/01/2023 01/13/2023
Bid Auth. Approval 07/01/2023 07/05/2023
Construction Approval 07/22/2023 07/21/2023
Project Closeout 12/30/2023 12/14/2023
Audit Date   12/14/2023
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 0 0
Right of Way 0 0
Total Design 0 0
     
Construction Engineering 0 19,298
Construction Contract 475,000 522,669
Other Construction 0 0
Total Construction 475,000 541,967
     
Funding Surplus - 22,283  
Total TIB Funding 452,717 541,967

Local Funding Partners

Funding Amount Percent
ABERDEEN 89,250 16.5%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 89,250 16.5%

Project Description

2 inch grind and overlay

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments