TIB Project Information
City of Burlington's 2023 Overlay Award
3-W-159(010)-1
3-W-159(010)-1
2023 Overlay Award
Multiple Locations
FY 2024 Arterial Preservation Program
Current Phase : Audit
Total TIB Funding : $617,813
County: Skagit | Legislative District: 40 | Project Length: 1.30 | TIB Engineer: Chris Langhoff | Last Payment Date: 11/15/2023
Project Information
Lead Agency | BURLINGTON |
Funding Year | 2024 |
Program | APP |
Current Phase | Audit |
Legislative District | 40 |
Congressional District | 2 |
Federal Route Number | 7319 |
Project Length | 1.30 mi. |
ADT | 0 |
Functional Class | Minor |
Type of Work | Resurfacing |
Project Contact | Brian Dempsey |
Contact Email | briand@burlingtonwa.gov |
TIB Engineer | Chris Langhoff |
Last Payment Date | 11/15/2023 |
Cultural Resource Assessment | Not Required |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 12/02/2022 | |
Delayed Project Date | 07/01/2025 | |
DAHP Assessment Date | ||
Predesign Approval | ||
Design Approval | 02/01/2023 | 12/20/2022 |
Bid Auth. Approval | 05/15/2023 | 04/13/2023 |
Construction Approval | 06/01/2023 | 05/11/2023 |
Project Closeout | 11/01/2023 | 11/02/2023 |
Audit Date | 11/15/2023 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 49,333 | 13,000 |
Right of Way | 0 | 0 |
Total Design | 49,333 | 13,000 |
Construction Engineering | 49,333 | 13,000 |
Construction Contract | 493,333 | 700,912 |
Other Construction | 0 | 0 |
Total Construction | 542,666 | 713,912 |
Funding Increase | 25,814 | |
Total TIB Funding | 617,813 | 726,912 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
BURLINGTON | 109,099 | 15.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 109,099 | 15.0% |
Project Description
2 inch overlay
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |