City of Sedro Woolley's Cook Road Overlay
3-W-126(009)-1
3-W-126(009)-1
Cook Road Overlay
W C/L to W Ferry St
FY 2024 Arterial Preservation Program
Current Phase : Audit
Total TIB Funding : $379,370
County: Skagit | Legislative District: 39 | Project Length: 0.48 | TIB Engineer: Chris Langhoff | Last Payment Date: 01/02/2024
Project Information
Lead Agency | SEDRO WOOLLEY |
Funding Year | 2024 |
Program | APP |
Current Phase | Audit |
Legislative District | 39 |
Congressional District | 2 |
Federal Route Number | 7381 |
Project Length | 0.48 mi. |
ADT | 0 |
Functional Class | Minor |
Type of Work | Resurfacing |
Project Contact | David Lee |
Contact Email | dlee@sedro-woolley.gov |
TIB Engineer | Chris Langhoff |
Last Payment Date | 01/02/2024 |
Cultural Resource Assessment | Not Required |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 12/02/2022 | |
Delayed Project Date | 07/01/2025 | |
DAHP Assessment Date | ||
Predesign Approval | ||
Design Approval | 02/01/2023 | 12/16/2022 |
Bid Auth. Approval | 07/01/2023 | 06/21/2023 |
Construction Approval | 07/30/2023 | 07/21/2023 |
Project Closeout | 12/31/2023 | 12/15/2023 |
Audit Date | 01/02/2024 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 12,750 | 7,061 |
Right of Way | 0 | 0 |
Total Design | 12,750 | 7,061 |
Construction Engineering | 17,000 | 7,131 |
Construction Contract | 422,359 | 432,125 |
Other Construction | 0 | 0 |
Total Construction | 439,359 | 439,256 |
Funding Surplus | - 72,739 | |
Total TIB Funding | 379,370 | 446,317 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
SEDRO WOOLLEY | 66,947 | 15.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 66,947 | 15.0% |
Project Description
2 inch overlay
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |